Answer:
Brad would likely to react by reducing the efforts on future projects.
Explanation:
In accordance with the equity theory, it states that if an employee feels or perceive inequity, then they will try to create equitable exchanges of their rewards and their efforts. The common reaction in this situation would be is to reduce the efforts on further or future project.
Answer:
Product A, then Product C and finally Product B
Explanation:
The unit profit = Selling price per unit - Variable cost per unit - Fixed cost per unit
Unit Profit of product A = $21 - $11 - $5 = $5
Unit Profit of product B = $12 - $7 - $3 = $2
Unit Profit of product C = $32 - $18 - $9 = $5
The profit of each product in 1 machine hour = 1 hour/ Machine hours per unit * Unit Profit
Profit of Product A in 1 hour using machine = 1/0.2 * $5 = $25
Profit of Product B in 1 hour using machine = 1/0.5*$2 = $4
Profit of Product C in 1 hour using machine = 1/0.2* $5 = $25
Product A & Product C have same profit in 1 hour machine, then we have to consider Direct labor hours per unit which product A is 0.4 while product C is 0.7. It means Product C is more costly in direct labour than Product A.
In short, then the ranking of the products from the most profitable to the least profitable use of the constrained resource is Product A, then Product C and finally Product B
Answer:
23.68%
Explanation:
The computation of the cost of not taking a cash discount is shown below:-
Cost of not taking a cash discount = [Discount percentage ÷ (100% - Disc.%)] × (360 ÷ (Final due date - Discount period))
= (2% ÷ 98%) × (360 ÷ (50 - 19))
= 2.04% × 11.61
= 23.68%
Therefore for computing the cost of not taking a cash discount we simply applied the above formula.
<span>If airlines are going to mine data from a captive audience several thousand feet in the air then they need to make a bigger deal of noting it. Much like the safety demonstration, before take off they should include a brief statement and have a Q & A sheet in the seat back. In this day and age protecting personal information is a touchy subject and not everyone is aware of that. You would think with the negative press for airlines these days and the huge debacles of cyber attacks and information leaks that airlines would be a bit more transparent on this practice.</span>
Answer:
Free slack.
Explanation:
In project management, free slack refers to the amount of time that a certain task can be delayed and not affect the completion time of the general project. Slack time can be considered "just in case" time, because even though delays should be minimized, rarely you can eliminate them completely, and slack time gives you a little extra room for managing projects.
In this case, the free slack time is 10 days, and this delay will consume 9 of them.