Answer:
The correct answer is E. master production schedules.
Explanation:
Master production schedules is not an input to the aggregate planning process all other options are its input,
Aggregate planning process is an attempt to respond to predicted demand within the constraints set by product, process and location decisions.
Hence, master production schedules is not a relevant input for this planning process but can be a result of the aggregate planning process. In other words master production schedule is formed after aggregated planning has been completed.
Answer: overturned prohibitions on interstate banking and branching(D)
Explanation:
The Riegle-Neal Act of 1994 was signed into law by former United States of America president; President Bill Clinton in September 1994. The Riegle-Neal Act of 1994 removed many obstacles that were encountered by banks that want to have branches in other states.
The Riegle-Neal Act of 1994 also provided uniform set of rules for the banks in each state. It allowed interstate banking nationwide for the first time, by allowing well-managed, and well-capitalized banks to get banks in other states.
Answer:
The correct option is A,devoting resources to researching and developing new products that will be more durable than competitors'
Explanation:
Creating sustainable advantage means that the company is able to do something very difficult for competitors to copy.
Sustainable advantage is not about cost reductions,is about a perceived value added to products or services not seen anywhere else.
If customers upload their designs for the company to produce, it does not necessarily mean the product is fit for purpose, as the company does not have full control over it.
Answer:Manufacturing costs assigned to completed units = $1143192
Explanation:
Material Costs = $600 000 (added at the beginning)
Conversion costs = $642600 incurred uniformly through out the process
Units Started = 100 000
Units on hand = 8000 units 40% complete
Units completed = 100 000 - 8000 = 92000 units
Percentage of units completed = 92000/100 000 = 92%
Material costs = $600 000 x 92% = $552000
Conversion Costs = $642 600 x 92% =$591192
Manufacturing costs assigned to completed = $552000 + $591192
Manufacturing costs assigned to completed units = $1143192
Answer:
See below.
Explanation:
Any cost that adds functionality to a capital asset or makes it usable is generally capitalized. These includes all the first time transit costs and or any installation costs. These costs are usually associated with the product as a one time cost rather than recurring annually.
The total cost then for the machine that is capitalized is,
= 180,000 + 4600 + 12000 = $196,600
The discount of 5% is deductible as this was not paid and will not be capitalized. So net total capitalized cost,
10-ton Draw = $196,600 - (180,000*0.05) = $187,600
Hope that helps.