The answer is: 48 hours
If the vessel operator is knowingly aware of the situation and decided not to file a written report for the victim, the vessel operator will be exposed to several risk of crime if the wound managed to took the victim's life because the court will seem him/her as responsible in the death
Answer:
Q' = 213.80
Explanation:
P(d): production rate per day = 200
Ic: Installation cost = 120
D: Demand = 8000
D(d): demand rate per day = 32
Uc: Unit cost (holding) = 50
Applying into Production order quantity model formula

The future worth of the periodic payment, in this case, annual, can be calculated through the equation,
FV = P x ((1 + r)^n - 1)/ r))
where FV is the future value, P is the periodic payment, r is the interest rate, and n is the number of years. Substituting the known values,
2,000,000 = P x ((1 + 0.06)^30 - 1)/ 0.06))
The value of P from the equation is $25,297.82
Hence, the answer to this item is the fourth choice.
Answer:
The book value of the machine at the end of 2021 is $620000.
Explanation:
The straight line depreciation allocates a constant depreciation expense throughout the useful life of the machine. The straight line depreciation expense can be calculated using the following formula,
Depreciation expense per year = (Cost - Residual value) / estimated useful life
Depreciation expense per year = (1000000 - 50000) / 5 = $190000 per year
The book value of asset is the value of the asset calculated by deducting Accumulated depreciation from its cost.
The book value of the machine at the end of 2021 will be the, considering the depreciation expense for year 2021 has been charged,
Accumulated depreciation till 2021 end = 190000 for Year 2020 + 190000 for Year 2021 = $380000
Book value at the end of 2021 = 1000000 - 380000 = $620000
Answer:
Directive PMO
Explanation:
A project management office(PMO) refers to creation of groups and departments within an organization so as to define standards and to ensure those standards are met.
In a directive form of project management office, it completely takes over projects and allots resources, and assigns project managers to projects.
In such a form of Project management office, the project managers are supposed to report to such directive offices.
In the given case, since Fran reports to such a PMO form which assumes control of the projects and manages the project, this is a directive form of project management.