Answer:
c.
Explanation:
the product is a "me-too" and contains no new technology or points of difference
Price skimming is a pricing strategy in which a marketer sets a relatively high initial price for a product or service at first, then lowers the price over time
Answer:
Deitz Corporation
Cash Budget
For the Quarter ended March 31, 2020:
Beginning balance $33,300
Cash Collections From Customers 205,350
Sale of Equipment 3,330
Total available cash $241,980
Cash Payments:
Direct materials $47,730
Direct labor 77,700
Manufacturing overhead 38,850
Selling & Administrative 49,950
Purchase of Securities 15,540 $(229,770)
Ending Balance $12,210
Minimum Balance 27,750
Shortfall $15,540
Explanation:
Deitz Corporation uses this Cash Budget which it has prepared to understand its financial needs for the next quarter. For example, with the minimum balance of $27,750 most likely based on past experience the corporation will start making arrangements for some outside funds to the tune of $15,540 or more to meet its cash needs for the first quarter.
Solution:
(1) Maximum possible $25,000 deduction before phase-out
(2) Maximum deduction phase-out is $22,500
[($145,000 AGI - 100,000) × 0.5]
(3) Current year overall loss $2,500 (1) - (2)
(4) Rental loss in current year $8,000
(5) Current year leasing deficit of 2,500 dollars, Lesser of (3) or (4)
Passive loss carry forward $5,500 (4) - (5)
Answer:
Total cost = Total ordering cost + Total holding cost
Total cost = DCo + QH
Q 2
Where
D = Annual demand
Co = Ordering cost per order
Q = EOQ
H = Holding cost per item per annum
D = 40,000 units
Co = $48
H = 18% x $8.00 = $1.44
EOQ = √2DCo
H
EOQ = √2 x 40,000 x $48
$1.44
EOQ = 1,633 units
Explanation:
EOQ equals 2 multiplied by annual demand and ordering cost divided by holding cost per item per annum. The holding cost per item per annum is calculated as holding cost rate multiplied by unit cost.
First of all, I will try to get to know people who were assigned to me. as I will have 75 tasks and equality is very important to me, I will give each person 25 task. if they will have some problems with given task I will try to help them or change their tasks so they can be more comfortable with their work. As a leader, i will do work as well, if my team will have some problems i will listen to them and solve those problems together.