Answer:
C-chart is the best suited for this since it is widely used to determine if the defects or returns are within the control limits or not.
Mean = average = 8 per day
Z=3
UcL = mean + 3[square root of mean]= 8+ 3 (Sq root of 8) = 16.48
LcL= mean - 3[ square foot of mean] = - 0.485
So the returns are within the control limits.
Answer:
is the practice of posting a discrete schedule of declining prices for different ranges of quantities
Explanation:
In the case of the second degree price discrimination, the firm should chares the different kinds of the prices as per the quantity demanded i.e. if the large quantities are ordered so it should be charged at the less price and if the small quantities are ordered so it should be charged at the high prices. The motive behind this is to motivate the bulk sales that means when the buyer purchased the products in bulk so he will get the high discounts
Therefore the third option is correct
Answer:
2190 ; 2560 ;
$778.2
Explanation:
Total worth of gasoline sold = 16003.50
Cost of regular = 3.30
Cost of premium = 3.45
Let :
premium Gallon sold = x
Regular gallon sold = 370 + x
Hence, mathematically;
(3.45*x) + (3.30 * (x + 370)) = 16003.50
3.45x + 3.30x + 1221 = 16003.50
6.75x = 16003.50 - 1221
6.75x = 14782.5
x = 14782.5 / 6.75
x = 2190
Premium Gallon sold = 2190 gallons
Regular gallon sold = 2190 + 370 = 2560 gallons
Profit per regular gallon sold = $0.15
Progit per premium Gallon sold = $0.18
Total profit = (2190 * 0.18) + (2560 * 0.15) = $778.2
Answer:
8,000 units need to be accounted for
Explanation:
The Weighted Average method Calculates the cost per unit by Adding the costs in Opening Work in Process and the Costs added in process department during the period. This cost is then divided by the the Sum of units in closing Work in Process and units of Completed goods.
The Units that needs to be Accounted for is the <em>Sum of</em> the units in Opening Work In Process and the units Transferred into the Assembly Department.
45N + 400M + 20P ≥ 45 is the constraint that limits the amount of time the writer will work each week.
Explanation:
Integer constraints limit any or all variables to only allow integer values in the optimisation issue. It allows for precise simulation of situations that include discrete numbers (such as equity shares) or decisions yes or no.
Both "limits" and "restrictions" are "restrictions," which may be the broadest word to denote anything that prohibits a entity or a mechanism from happening. "Standards" and "controls" typically feel like standing back, where "stretches" sound like being alone.