OleMash [197]
2 years ago
15

The following events pertain to Jasper Corporation: May 1 Jasper purchased office supplies of $3,000 on account. May 5 The offic

e supplies were shipped to Jasper. May 8 Jasper used these office supplies for a one-time event. May 9 Jasper paid $3,000 cash for the office supplies purchased on May 1. Using cash-basis accounting, on which date should Jasper record supplies expense?
Business
1 answer:
Alisiya [41]2 years ago
3 0

Answer:

May 9th

Explanation:

When a company uses a cash basis accounting, it records its revenues and expenses on the day that the money is received or paid respectively. In this case, the supplies were purchased on May 1st, delivered on May 5th, used on May 8th, but paid on May 9th. And the date of the payment is what matters here.

The journal entry should be as following:

May 9, office supplies.

Dr Supplies expense 3,000

    Cr Cash 3,000

You might be interested in
Neutronics makes four different models of gas identifiers. Next year, the company anticipates total overhead costs of $2.5 milli
Rainbow [258]

Answer:

Predetermined manufacturing overhead rate= $33.33 per direct labor hour

Explanation:

Giving the following information:

Next year, the company anticipates total overhead costs of $2.5 million.

Estimated direct labor hours= 75,000

<u>To calculate the predetermined manufacturing overhead rate we need to use the following formula:</u>

Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base

Predetermined manufacturing overhead rate= 2,500,000/75,000

8 0
2 years ago
Ethan's job as an accounting assistant was recently modified to include reconciling bank accounts and making deposits, two tasks
jek_recluse [69]

Answer:

The correct option is C,job enrichment

Explanation:

Job enlargement refers adding additional tasks to an employee's job description and it is done for different reasons. The chief possible motive for job enlargement could be prepare the employee for a higher role.

Satisficing on the job involves ensuring one is able to attend to tasks one is saddled with in order to achieve a balance between different stakeholders' expectations instead of prioritizing one's stakeholder's need over another.

Job enrichment is a way of encouraging employees to give out their best output by assigning to them jobs previously reserved for more senior employees

Job design implies making decision on a job description by considering tasks that could be combined and performed by a single employee

Job development is about appraising an employee with a view to discovering his growth needs on the job and make adequate arrangement in terms of training to enable the employee to bridge the skills gap

The bone contention here is between options A and C,but C is preferred since the additional tasks are tasks previously meant for one's managers.

7 0
2 years ago
A certain project has three activities on its critical path. Activity A’s normal completion time is five days. It can be crashed
Snowcat [4.5K]

Answer:

Acitivy B should be crashed first by 2 days and Activity B has a crash cost per days of $25, it will be crashed for a total of $50.

Explanation:

activity A =

normal time (NT) = 5 days

Normal cost (NC) = $0

crash time (CT) = 3 days

Crash cost (CC) = $500

crash cost per day = [CC - NC]/[CT - NT] = $250/day

activity B:

normal time (NT) = 6 days

Normal cost (NC) = $0

crash time (CT) = 4 days

Crash cost (CC) = $50

crash cost per day = [CC - NC]/[CT - NT] = $25/day

activity C:

normal time (NT) = 8 days

Normal cost (NC) = $0

crash time (CT) = 3 days

Crash cost (CC) = $1000

crash cost per day = [CC - NC]/[ CT- NT] = $200/day

The activity that takes the least cost to speed up is the first one to be crashed. from the computations, activity B takes the least cost to speed up, so the project manager should crash activity B first by 2 days.

Therefore, Acitivy B should be crashed first by 2 days and Activity B has a crash cost per days of $25, it will be crashed for a total of $50.

6 0
2 years ago
When bringing to market a new product like the MotorolaOne Zoom, the actual product launch takes place in the __________________
AnnZ [28]

Answer:

Option E: Commercialization

Explanation:

The marketplace is simply dynamic and undergoes different changes and the demand rate for products is also do change. Companies evaluate their already made or existing product line, update it and tries to fit into the standard of their consumers.

In the new product development strategies, companies makes a unique new product development strategy to limit the overuse of time and resources through the method of, organize planning and research, understanding what customer really want thereby definitely resourcing of the said project.

In commercialization, it entails the new product launching procedures (processes). It usually needs heavy promotion and product distribution throughout the network.

6 0
1 year ago
Imagine that you are an executive at a large bank. You have been tasked with overseeing your company's implementation of an enti
Afina-wow [57]

Answer:

My straight answer is you need a Diverse team with somewhat a high level of management with Gain Sharing Program as the incentive programme.

Explanation:

Since the question is long, I'll make it shorter. The team is New, the goal is wide, the team's autonomy (working independence) is not much strong.

A Diverse team is required as the set of tasks needed to be done requires different skill sets. (like law, tax, etc.)

Although the team is highly talented, they are new and not much experienced. So, a high level of management is required at the beginning until the team stabilizes.

Since its a new and diverse team, team spirit has to be established. An unfitting rewarding system could be the very beginning of various conflicts, trust issues and jealousy among peers in the group. Eventually destroying the team altogether.

Gain Sharing program mainly focus on improving the team productivity through participation, involvement and creative innovation. Eventually the entire team's productivity goes up and then the entire team is rewarded.

5 0
2 years ago
Other questions:
  • On april 1, griffith publishing company received $1,548 from santa fe, inc. for 36-month subscriptions to several different maga
    9·2 answers
  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturin
    8·2 answers
  • Woodmier Lawn Products introduced a new line of commercial sprinklers in 2020 that carry a one-year warranty against manufacture
    10·1 answer
  • On March 1, Job 10 had a beginning balance of $500. During March, direct materials of $800 and direct labor of $300 were added t
    10·1 answer
  • In a company's standard costing system, direct labor-hours are used as the base for applying variable manufacturing overhead cos
    15·1 answer
  • A company experiences a stock split due to poor performance. Ariana's initial investment
    5·2 answers
  • Larry recently invested $24,400 (tax basis) in purchasing a limited partnership interest in which he will have no management rig
    13·1 answer
  • Why is it important for HR management to transform from being primarily administrative and operational to a more strategic contr
    14·1 answer
  • An industry consists of three firms with sales of $300,000, $700,000, and $250,000. a. Calculate the Herfindahl-Hirschman index
    8·1 answer
  • Phil Frugal has been saving his pennies since he was 5 years old. He is now 45 and deposits his savings in a bank. His pennies t
    8·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!