Answer:
Determining whether the Performance Matches the Standard
Explanation:
In the Control process there are four steps:
Step 1. Establish Standards and Methods for Measuring Performance
Step 2. Measuring the Performance
Step 3. Determination of Whether the Performance Matches the Standard
Step 4. Taking Corrective Action.
In this example, the first and second steps have been completed, step 3 has just been done by Charlene since she discovered that the number of handbags produced in one week by 45 employees was 375 against the set target of 450 handbags.
Charlene is yet to complete step 4.
Answer:
Consider the following information for three stocks, A, B, and C. The stocks' returns are positively but not perfectly positively correlated with one another, i.e., the correlations are all between 0 and 1. Expected Standard Stock Return Deviation Beta
A 10% 20% 1.0
B 10% 10% 1.0
C 12% 12%1.4
Portfolio AB has half of its funds invested in Stock A and half in Stock B. Portfolio ABC has one third of its funds invested in each of the three stocks. The risk-free rate is 5%, and the market is in equilibrium, so required returns equal expected returns. Which of the following statements is CORRECT?
Question 13 options:
a) Portfolio ABC's expected return is 10.66667% correct answer
. b) Portfolio AB has a standard deviation of 20%.
c)Portfolio ABC has a standard deviation of 20%.
d)Portfolio AB's required return is greater than the required return on Stock A.
e)Portfolio AB's coefficient of variation is greater than 2.0
Answer:
The NPV of the project is $974.
Explanation:
The net present value is the today's value of a stream of cash flows. The net present value will be the sum of all the expected future cash flows from a project less the initial investment required for the project and it is used to evaluate the investment decisions.
The net present value of an investment project will be:
NPV = CF1 / (1+r) + CF2 / (1+r)^2 + ... + CFn / (1+r)^n - Initial investment
or
If the cash flows are constant or of same amount through out, occur after the same interval of time and are for a defined period of time, they become an annuity and the NPV of such a project can be calculated by,
NPV = (Cash flow per period * Present value of Annuity factor) - Initial cost
The NPV of this project will be = (2000 * 2.4869) - 4000 = 973.8 rounded off to $974
<span>Potential investment of the Tackle shop = $750000
Depreciation Tax Shield = $35000
Tax Rate for 2016 = 20% => T = 0.2
So we have a equation for depreciation, which goes like
Depreciation Tax Shield = T(Depreciation )
=> 35000 = 0.2(Depreciation)
So the Depreciation = 35000/0.2 which gives $175,000
Depreciation = $175,000
So C is correct.</span>
Answer: $1,256
Explanation:
Milo makes 6% on the sales that he makes.
The $75.36 that he made from this sale is therefore 6% of the cost of the item sold.
Assuming the item was x, the cost is;
6% * x = 75.36
x = 75.36/6%
x = $1,256