Answer:
a. an informative process speech
Explanation:
An expository speech is one that explains the processes involved in doing an activity. It is meant to inform the audience on processes involved in executing a task.
In this scenario strip mining is the process of removing the top layer of soil in order to gain access to a mineral. This process is opposed to digging of deep holes to access minerals. The method is commonly used in coal reserves.
An expository speech by Katerina on strip mining will be an informative process speech on this process of mining minerals
Answer:
This type of effort is known as <u>collaboration</u>
Explanation:
Collaboration among businesses involve them <u>working together to achieve common business goals which could be </u><u>manufacturing </u><u>or marketing goals.</u>
In such instances, the businesses could combine their resource and share expenses among themselves and this helps reduce costs and increase efficiency.
Answer:
(a) The Vasquez construction is the principal, the surety is the party that underwrites the contract and local school board is the obligee.
(b) If Vasquez fails to finish the contract, then the surety will be required to pay for the loss suffered by the obligee due to the contract failure.
(c) In a surety bonds contract, the surety has a legal right to get back the losses from the principal.
Explanation:
Solution:
(a) Under a performance bond contract, the owners assures that the work will be completed within a specific time frame and contract specification.
In this example given, the Vasquez construction is the principal, the surety is the party that underwrites the contract and local school board is the obligee.
(b) If the Vasquez construction fails to complete or finish the contract, then the surety will be obliged to pay for the loss suffered by the obligee due to the failure of the contract.
(c) In a surety bond contract, the surety has a legal right to recover the losses from the principal. for this later on, the surety can recover it's loss from the principal.
Answer:
1,370.85 Unfavorable
Explanation:
Standard rate
:
= Budgeted variable overhead costs ÷ Budgeted direct labor hours
= $13500 ÷ 640
Direct labor hours = $21.09 per direct labor hour
Standard time to produce goods
:
= Budgeted direct labor hours ÷ Production volume
= 640 ÷ 6,400
= 0.10 hours
VOH Efficiency Variance
= ( SH − AH ) × SR
where,
SH are standard direct labor hours allowed
AH are the actual direct labor hours
SR is the standard variable overhead rate
(SH − AH ) × SR
= [(4,200 × 0.10) - 485] × $21.09
= (420 - 485) × $21.09
= 1,370.85 Unfavorable
Answer:
6) H0: μ≥ 7.4 versus H1: μ< 7.4
7) - 1.28
8) - 1.50