Answer: $184.34
Bess issued four checks with amounts $175.17, $175.53, $175.35,and $184.34. With the total amount she issued, she expected her balance based on her cash register to be $869.96, but as per bank statement, her balance is $1054.13.
To get the amount of check which is not cleared yet, we have to deduct the balance in the cash check register from that of the bank statement:
$1054.13-$869.96 =184.17
$184.34 is the best answer because it is the last he wrote and the discrepancy of 0.17 may be due to some bank charges Bess had not recorded.
Rick gave his son $100 to buy food and drinks. His son returned with $25.50 in change. Therefore the amount spent was
$100 - $25.50 = $74.50.
Let
x = number of hot dogs bought (at $3.50 per hot dog).
y = number of milk shakes bought (at $8 per milk shake).
There were 8 orders of soda at $5 per soda.
The total order is $74.50, therefore
3.50x + 8y + 8*5 = 74.50
Simplify to obtain
8y = 74.5 - 3.5x
y = 4.3125 - 0.4375x
We must have whole numbers (integers) for x and y.
Create a table that varies x from 0 to 8, and look for y to be an integer, as shown below.
x y
--- -------
0 4.3125
1 3.8750
2 3.4375
3 3
4 2.5625
5 2.1250
6 1.6875
7 1.2500
8 0.8125
Because we cannot have fractional values for either x or y, the solution is x=3, y=3
Answer:
3 hot dogs, 3 milk shakes, and 8 sodas.
oi oi siempre todos
Explanation:
mmm... los dias es ooh oop
Answer:
The issues that arises between the Faraj and Siegel can be discussed by three different groups in resolving the contract agreement.
Note: Kindly find an attached copy of the complete question below.
Explanation:
Solution
In this case between Faraj and Siege'ls building contractors the following issue are discussed by three groups as follows:
(1) The contractor can increase the price of finishing construction based on inflation and the cost of raising materials during inflation prices for the materials increases or goes up and this will affect the customer gradually.
(2) Faraj will not pay the additional amount requested by Siegel because according to the contract the amount she has to pay is $153,000
(3) Issues or problems that might come up during construction is listed below:
- Poor communication
- Not feasible or impractical forecasting
- The unavailability of structure
Alert personnel when credentials are about to be expired