Manufacturing overhead expense volatility will be determined by subtracting the overhead cost of output from the total overhead cost of production according to the adjustable budget.
(Manufacturing overhead cost as per flexible budget) =
(Actual units x Variable manufacturing overhead per unit +Fixed manufacturing overhead )
= (5,050 x $1.30)+ $41,500 = $48,065
Actual manufacturing overhead cost = $47,905
Therefore, Manufacturing overhead spending variance
= $48,065 - $47,905 = $160
The deviation is positive as the real expense is smaller than the adjustable cost of the program.
The correct answer is 2; Corinne would use the process of integration and sit everyone down together to talk it through.
Further Explanation:
Since this type of issue needs to be addressed immediately, Corinne would need to sit everyone down and talk it through to get to the bottom of the sexual advances. When she does this it is called the process of integration. During this process, she will discuss the employees concerns and take their statements.
During the discussion, the employees will be guaranteed anonymity. The complaints will all be taken seriously, and an investigation will be started immediately. The supervisor may be put on administration leave while the investigation is ongoing.
Learn more about sexual harassment in the workplace at brainly.com/question/10185961
#LearnwithBrainly
Answer:
Cappuccino machines should be produced in Atlanta and coffee makers in Fort Worth. The Fort Worth facility would need to operate 100 hours per week and the Atlanta facility would need to operate 140 hours per week.
Total costs associated to operating the facilities = ($2,400 x 100) + ($600 x 140) = $324,000
Explanation:
Since there is not constraint regarding the total number of labor hours that each plant can operate, then we must choose the plant that operates at the lower cost. The only restriction is total time = 7 days x 24 hours = 168 hours per week:
production costs Atlanta:
coffee maker = $600 / 160 = $3.75 per unit
cappuccino machine = $600 / 200 = $3 per unit
production costs Fort Worth:
coffee maker = $2,400 / 800 = $3 per unit
cappuccino machine = $2,400 / 200 = $6 per unit
Cappuccino machines should be produced in Atlanta and coffee makers in Fort Worth. The Fort Worth facility would need to operate 100 hours per week and the Atlanta facility would need to operate 140 hours per week.
Can you dm me for the answer I’m not home rn I’m trying to help out a lot of people
These are the factors by how it shifts the current demand curve to a new position:
Shifts left
- 2% rebate on a Toyota Camry, a substitute good
- Big sale coming in three months
Shifts right
- Free brake inspections
- Consumers' income increases by 10%