Answer:
The answer and procedures of the exercise are attached in a microsof excel document.
Explanation:
After a research on internet I found the exercise and the questions better explained. The correct formulation is attached as an image. Please let me know that we are looking to the same exercise.
Please consider the data provided by you. If you have any question please write me back. All the exercises are solved in a single sheet with the formulas indications.
Answer:
Jackson's target total cost of producing and selling 6 million cans of paint of $31,800,000 will enable it to reach stockholders' profit goals of $6 million.
The implication is that it should not allow its total costs (Production and other business expenses) to exceed $37,800,000.
This is because its sales revenue will be equal to $43,800,000 (6,000,000 * $7.30).
As such, Jackson can produce a can of paint for $5.30. It can also incur an average business expense of $1.00 per can to maintain and reach its $6 million profit target.
Explanation:
Profit is the difference obtained after deducting all costs from the revenue. There are some profit stages. The first is the gross profit, which considers the sales revenue and the cost of goods sold. The next profit stage is the operating profit, which subtracts the business running expenses from the gross profit. There are also profits before and after interest and taxes. The after tax profit is also called the net income or net profit. If it is negative, then it is called the net loss. It is from the net income that distributions are made to stockholders in the form of dividends while a part is retained in the business to increase its capital stock or stockholders' equity.
I wanna say d would be the answer but it could also be banking services
Answer:
15.8%
Explanation:
Process Cycle Efficiency= Value Added time/ Lead time
Value-added time is the time spent process and activities on improving or adding usefulness to a product.
Lead time is the time between the order received and order supplied to the customer
Here,
PCE= (3)/(2.5+5+10+1.5) ×100
PCE=15.8%
Answer:
1 Ask Fred to run team meetings in order to get to know people more quickly.
Explanation:
This alternative is the most effective to help Fred adjusting to the team and build cultural competence. There are 2 reasons: 1. The other options did not allow Fred of socializing with team members and take a lesson of them. 2. Cultural competence goes beyond knowing business rules and how to make decisions.