2 years ago
14

A project manager forgets to assess how national holidays and team member vacations will affect the project’s completion date. N

ow, because of team member time off, the project delivery will be two weeks late. What flexible planning strategy could the project manager have used to avoid the delay?
Business
1 answer:
solong [7]2 years ago
5 0

The flexible strategy is used to avoid the delay in assessing the external constraints.

The following information regarding accessing external constraints:

  • It could be thrust upon an organization.
  • It permits for uncovering the things that are beyond the control.
  • The example involved national holidays or sick leaves.

If we accessing the external constraints so the delay could be avoided.

So, The other options seem incorrect

Therefore we can conclude that the flexible strategy is used to avoid the delay in assessing the external constraints.

Learn more about the external constraints here: brainly.com/question/17156848

You might be interested in
The Flores Family loves to go sailing on the weekends. Mr. Flores has decided to purchase a more spacious sailboat. The sailboat
zavuch27 [327]

Answer:

$367.86

Explanation:

To calculate this, we use the formula for calculating future value annuity (FVA) due as follows:

FV = M × {[(1 + r)^n - 1] ÷ r} × (1 + r) ................................. (1)

Where,

FV = Future value of an annuity or the cost of sailboat =  $20,000

M = Amount of each annuity  or to deposit monthly = ?

r = Monthly interest rate  = 0.06 ÷ 12 = 0.005

n = number of months = 4 years × 12 = 48

Substituting the values into equation (1), we have:

20,000 = M × {[(1 + 0.005)^48 - 1] ÷ 0.005} × (1 + 0.005)

20,000 = M × 54.3683213801713  

Making M the subject of the formula and solve, we have:

M = 20,000 ÷ 54.3683213801713  = $367.86

Therefore, Mr. Flores should deposit $367.86 in this account at the beginning of each month to be able to pay cash for the sailboat in 4 years.

8 0
2 years ago
Which of the following statements is not correct?
arlik [135]

Answer:

d. The cash budget must be prepared prior to the sales budget because managers want to know the expected cash collections on sales made to customers in prior periods before projecting sales for the current period.

Explanation:

  • From the statements the cash budget must be prepared in advance to the sales budget is not corrects. As the sales budget is prepared first and it establishes a format for the budget that is critical for the company successes and it thus consists of the different elements that depend in how a business is organized.
6 0
2 years ago
Vaughn Corporation acquires a coal mine at a cost of $460,000. Intangible development costs total $115,000. After extraction has
Elenna [48]

Answer:

Depletion expense A/c Dr $84,525

       To Accumulated depletion A/c

(Being the depletion expense for the first year is recorded)

Explanation:

The journal entry is presented below:

Depletion expense A/c Dr $84,525

       To Accumulated depletion A/c

(Being the depletion expense for the first year is recorded)

The computation is shown below

First we have to compute the depletion per ton which is calculated below:

= (Acquired cost of coal mine + Intangible development costs + fair value of the obligation - Sale value) ÷ (Number of estimated tons of coal extracted)

= ($460,000 + $115,000 + $92,000 - $184,000) ÷ (4,600 tons)

= $105

Now if 805 tons are extracted in first year, so the depletion would be

= 805 tons × $105

= $84,525

8 0
2 years ago
What are potential sources of error for bmi and w/h ratio?
VMariaS [17]
<span>Potential sources of error for bmi come from measurement errors. BMI is calculated by your height and weight. If the height is calculated by seeing how tall you are and measured by inches. If you are not standing straight and slouch you height measurement is not accurate. Weight is measured on a scale in pounds. One must remove clothes to get an accurate weight. If any of these measurements are off, the bmi will not correct.</span>
6 0
2 years ago
Read 2 more answers
A regional automobile dealership sent out fliers to prospective customers indicating that they had already won one of three diff
Bas_tet [7]

Answer:

the requirements are missing, so I looked for a similar question.

<em>a. How many fliers do you think the automobile dealership sent​ out? </em>

<em> b. Using your answer to​ (a) and the probabilities listed on the​ flier, what is the expected value of the prize won by a prospective customer receiving a​ flier? </em>

<em> c. Using your answer to​ (a) and the probabilities listed on the​ flier, what is the standard deviation of the value of the prize won by a prospective customer receiving a​ flier?</em>

a) the total fliers sent out = 31,246 + 1 + 1 = 31,248

b) expected value = [(1 x $28,000) + (1 x $100) + (31,246 x $5)] / 31,248 = $5.90

c) σ² = [($28,000 - $5.90)² x 1] + [($100 - $5.90)² x 1] + [($5 - $5.90)² x 31,246] / 31,248 = ($783,669,634.80 + $8,854.81 + $25,309.26) / 31,248 = $25,080.13

σ = √$25,080.13 = $158.37

4 0
2 years ago
Other questions:
  • The local classic car auction raised $12,000 for local charities, the mayor is designating the funds to the children’s hospital.
    14·2 answers
  • Scenario: Elly owns a small coffee shop. She has only one employee. One weekend, she decides to take a break from work. She is w
    11·1 answer
  • U Do It Centers deposited $3,200 in an account two years ago and is depositing another $5,000 today. A final deposit of $3,500 w
    11·1 answer
  • Rules of thumb rarely if ever lead to severe errors in the decision making process.a. Trueb. False
    6·1 answer
  • Training activities are said to be outsourced when they are provided by ________. in-house consultants company managers individu
    15·1 answer
  • Fasheh Corporation's relevant range of activity is 7,000 units to 11,000 units. When it produces and sells 9,000 units, its aver
    15·1 answer
  • Gig Harbor Boating is the wholesale distributor of a small recreational catamaran sailboat. Management has prepared the followin
    9·1 answer
  • ​Jack, an employee of Desert​ Sky, Inc., has gross salary for May of . The entire amount is under the OASDI limit of​ $118,500 a
    10·1 answer
  • Skippers Landing sells boats and provides mooring facilities for its customers. Skippers Landing sells the boats for $60,000 eac
    14·1 answer
  • The employees who physically move inventory items for storage or shipment
    8·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!