Answer:
DL, DM, and VOH.
Explanation:
Under the variable costing method, direct labor cost, direct material cost and variable manufacturing overhead cost are cost assigned to the product. administrative, fixed manufacturing overhead cost are not variable cost and hence cannot be assigned to a product under variable costing method. Variable costing methods considers only manufacturing costs that change in total with changes in production level.
A. allows you to diversify as opportunities develop.
Answer:
The overhead cost assigned to each unit of product B is $46.2 per unit.
Explanation:
Overhead absorbed in each product B can be calculated as under:
Overhead Absorbed = Overhead Absorption Rate * Absorption Basis
Here in this question, the absorption basis is Direct labor hours. So the direct labor hour per unit of Product B is 0.7 Hr and the OAR is $66.
By putting values in the above equation, we have:
Overhead Absorbed = $66 per unit * 0.7Hrs = $46.2 per unit
Answer:
E. Centralized Authority.
Explanation:
As Typhanie, a customer service representative with WestComm Wireless Services, was asked by one of her customers if WestComm would be interested in joining the chamber of commerce to meet potential customers and increase its contacts in the local business community. Typhanie believes this is a very good idea and approached her manager, Deondre, about becoming a chamber member. Deondre said to Typhanie, "Because the cost of membership is over $500 and you will have to leave the office to attend meetings, I will have to get approval from management above me." WestComm is an example of an organization with centralized authority.
In centralized authority, the decisions are made from the top level management or decisions are made from certain managers. Anyone can't make decisions by his or her own in this kind of management style. This system has many flaws as well. As we have seen here in this case, Typhanie is interested in going to chamber of commerce which definitely will be very good for the organisation but when she approached her manager Deondre, he said he even himself can't decide about it, he has to get the orders from his boss. Although the event can be good for the organisation but centralized decision making has made it almost impossible.
Answer:3.67,1
Explanation:
TE = (O + 4T + P) / 6
where,
TE = Pert Expected Time Duration,
O = Optimistic estimate, =2
T = Typical estimate,=3
P = Pessimistic estimate=8
TE = (O + 4T + P) / 6
=(2+4*3+8)/6
3.6666=3.67
σ = (P – O)/6
=(8-2)/6
=1