Answer: Apportionment
Explanation: Apportionment is also known as analogous estimating which is used when projects closely follow past projects in features and costs. As a result, in addition to good historical data, estimates regarding project feature, cost and duration can be made quickly, with little effort and reasonable accuracy to various segments of the current project. The method of apportionment is very common in projects that are relatively standard, but with little variation or customisation.
Answer:
$19,462
Explanation:
The computation of the cash and cash equivalent is shown below:
= Cash in bank account + Money market fund balance + petty cash balance + money orders
= $6,455 + $12,400 + $350 + $257
= $19,462
It includes only cash in bank account, balance in money market, petty cash balance and the money orders
All other information which is given is not relevant. Hence, ignored it
Answer:
china
Explanation:
if your traveling to china on business do not discuss business during meals .
Being forced to stand in the hot sunenduring beatingscatching diseases<span>getting shot</span>
Answer:
On IRR basis projects 1, 2, 3, and 5 will be selected.
On NPV basis projects 1, 3, 5, and 6 will be selected.
Explanation:
The firm will accept or choose all the project that has a higher or equal internal rate of interest than cost of capital. However, in the given case project 4 has a lower internal rate of interest (12 percent) than the cost of capital. Thus, projects 1, 2, 3, and 5 will be chosen by the firm. While the firm has budget constraints so it will have no money for projects 4 and 6.
The firm will select all the projects with positive NPV when there is no budget constraint. But in case of budget constraint, the firm will select the project that has high NPV. Thus, Project 1, 6, 3, and 5 will be selected and there will be no money left for projects 2 and 4.