Answer:
D. not joining FFA and joining HOSA instead
Explanation:
Answer:
0%
30%
Explanation:
Given:
Average return = 15%
Standard deviation = 15%
Computation:
On assuming 68% chance,
Lowest point = Average return - Standard deviation
Lowest point = 15% - 15%
Lowest point = 0%
Highest point = Average return - Standard deviation
Highest point = 15% + 15%
Highest point = 30%
Therefore, on 68%, Lowest point is 0% and highest point is 30%.
Answer:
Explanation:
The journal entry on April 13 for receipt of payment from customer is as follows:
Date Account title and explanation Ref Debit Credit
13-April Cash ($5000 - $150) $4,850
Sales discount ($5000* 3%) $150
Accounts receivable
$5000
(To record the receipt of payment from customer net of discount
Answer:
The projects which maximize Vanguard's shareholder wealth are Project A; Project B; Project D.
Explanation:
Projects which maximize the shareholder value are projects delivering Expected Returns which are higher than its risk-adjusted weighted average cost of capital (WACC).
As a result, Project A with Expected return of 15% and risk adjusted WACC of 12%; Project B with Expected return of 12% and risk adjusted WACC of 10%; Project D with Expected return of 9% and risk adjusted WACC of 8%; are the projects that maximize the shareholder's value.
On the other hand, Project C with Expected return of 11% and risk adjusted WACC of 12% is harmful to shareholder value.
Answer:
The correct answer is C.
Explanation:
Giving the following information:
Total Estimated total machine-hours (MHs) 10,000
Estimated total fixed manufacturing overhead cost= $45,800
Total Estimated variable manufacturing overhead cost- per MH= $1.90 + $2.10= $4
To calculate the estimated manufacturing overhead rate we need to use the following formula:
<u>Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base</u>
<u>Estimated FIXED manufacturing overhead rate=</u> (45,800/10,000)= $4.58