Answer:
$21,370
Explanation:
A composite unit is a set of different products grouped together in proportion to their sales mix. The unit is a basis for grouping products from different segments of an entity together with the aim of managing inventory levels, break even points, and sales.
The selling price of the composite unit can be calculated as follows:
||Bicycle model |No. of bicycles |Unit selling price |Total per composite unit
|Youth models| 5 | 440 | 2,200
|Adult models| 9 | 990 | 8,910
|Recreational models| 6 | 1,140 | <u>10,260</u>
Selling price per composite unit <u>21,370</u>
Answer:
$4,372.71
Explanation:
Here for reaching the difference in PV between the first and the second offer first we need to follow some steps which is shown below:-
Step 1
Total payment due = Per tire × Bought tires
= $80 × 600
= $48,000
Step 2
Present value factor of 8.4% for 1 year = 1 ÷ (1 + Rate of interest)^Number of years
= 1 ÷ (1 + 8.4%)^1
= 1 ÷ (1 + 0.084)^1
= 1 ÷ 1.084
= 0.92251
Step 3
First offer
Present value = Total payment due × Present value factor of 8.4% for 1 year
= $48,000 × 0.92251
= $44,280.48
Step 4
Second offer
One year payment = Bought tires × Per tire
= 600 × $45
= $27,000
Step 5
Present value = One year payment × Present value factor of 8.4% for 1 year
= 27,000 × 0.92251
= $24,907.77
Step 6
Total present value = Present value of second offer + Tires cost
= $24,907.77 + $15,000
= $39,907.77
Here we can see that first offer is higher than second offer
So,
The difference between the first and the second offer = First offer - Second offer
= $44,280.48 - $39,907.77
= $4,372.71
Answer:
The answer is E.
Explanation:
Total payment from customers is:
$537,400 + $737,500
= $1,274,900
Weighted average delay from customer A is:
($537,400/$1,274,900) x 3
=1.26 days
Weighted average delay from customer B is:
($737,500/$1,274,900) x 1
=0.58 day
Therefore, total weighted average delay is:
1.26 days + 0.58 day
=1.84days
Answer:
The total overhead variance in hours taken is 3,600 hours
The total overhead cost variance is $1,110
Explanation:
The variance is about the different between budget/ standard and actual figures.
Standard hours allowed for the work done is 22,200 hours; and the predetermined overhead rate is $5.75 per direct labor hour. So total cost budgeted for work done is $127,650 = $5.57 x 22,200 hours
The total overhead variance in hours taken = standard hours of 22,200 - actual direct labor hours of 18,600 = 3,600 hours
The total overhead cost variance = standard cost - actual cost = $127,650 - $126,540 = $1,110
Answer:
$375
Explanation:
If Johnson will use the desired gross margin percentage to determine the selling price of its products, they must use the following formula:
selling price per unit = total manufacturing costs per unit / (1 - gross margin)
Total manufacturing costs = variable manufacturing costs + total fixed costs + batch level fixed overhead = $2,350,000 + $1,200,000 + $200,000 = $3,750,000
total manufacturing cost per unit = $3,750,000 / 20,000 units = $187.50
selling price per unit = $187.50 / (1 - 50%) = $187.50 / 50% = $375