14

A company has a process that results in 12,000 pounds of Product A that can be sold for $8 per pound. An alternative would be to

process Product A further at a cost of $80,000 and then sell it for $14 per pound. Should management sell Product A now or should Product A be processed further and then sold?
Business
1 answer:
eimsori [14]2 years ago
8 0

Answer:

The correct answer is management should sell Product A now.

Explanation:

According to the scenario, computation of the given data are as follows:

Total production = 12,000 pounds

Sell price = $8 per pound

If process further, Cost = $80,000

Selling price = $14 per pound

So, If we sell the product without further process, than

Total sale value = 12,000 × $8 = $96,000

And, if we sell the product after further processing, then

Total sale value = (12,000 × $14) - $80,000

= $88,000.

As, sales value is more in selling the product without further process, so management should sell the product without further processing it.

You might be interested in
Which of the following is not an input to the aggregate planning process? A. demand forecast B. cost information C. policies on
ale4655 [162]

Answer:

The correct answer is E. master production schedules.

Explanation:

Master production schedules is not an input to the aggregate planning process  all other options are its input,

Aggregate planning process is an attempt to respond to predicted demand within the constraints set by product, process and location decisions.

Hence, master production schedules is not a relevant input for this planning process but can be a result of the aggregate planning process. In other words master production schedule is formed after aggregated planning has been completed.

6 0
2 years ago
Read 2 more answers
Hubbard Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-
Ghella [55]

Answer:

Instructios are listed below.

Explanation:

Giving the following information:

Hubbard Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During January, the kennel budgeted for 2,100 tenant-days, but its actual level of activity was 2,060 tenant-days.

Wages and salaries:

Fixed= $ 2,300

Variable=  $ 7.20

Estimated Wages and Salaries= 2,300 + 7.2*2,100= $17,420

3 0
2 years ago
Hodge Inc. has some material that originally cost $74,600. The material has a scrap value of $57,400 as is, but if reworked at a
Burka [1]

Answer:  If the material is reworked and sold, Hodge Inc. has a financial disadvantage of (- 4500).

Let's see why:

1) If we sell the material at its disposal value: We have a cost of $ 74600 and the income from sale would be $ 57400 =

57400 - 74600 = (-17200). We have a loss of $17200.

2) If we rework the material we will have an original cost of $ 74600, an additional cost for reworking of $ 1500 and the income from its sale would be $ 54400 =

54400 - (74600 + 1500) = (-21700) We have a loss of $ 21700.

Then comparing the 2 situations =

(-21700) - (-17200) = -4500. There is a financial disadvantage of $4,500 if the material is reworked instead of selling it as scrap.

6 0
2 years ago
Levine Inc., which produces a single product, had prepared the following standard cost sheet for one unit of the product.
sergeinik [125]

Answer:

material price variance (standard price - actual price) * quantity purchased

MPV= ( 3.30 - 3.50) 2300 =$460 Unfavorable

Material quantity variance = ( standard quantity - actual quantity) standard price

MQV = ( 1920 -2300) 3.30 = $1254 Unfavorable

Labour price (rate) variance = (Standard rate - actual rate) actual hours

LRV = (12- 11.8) * 280 = $56 Favorable

Labor hours variance = ( standard hours - actual hours) * standard rate

LHV = ( 240 - 280) * $12 = $480 unfavorable

Explanation:

the complete question:

Levine Inc., which produces a single product, has prepared the following standard cost sheet for one unit of the product. Direct materials (8 pounds at $3.30 per pound) $26.40 Direct labor (1 hours at $12.00 per hour) $12.00 During the month of April, the company manufactures 240 units and incurs the following actual costs. Direct materials purchased and used (2,300 pounds) $8,050 Direct labor (280 hours) $3,304 Compute the total price, and quantity variances for materials and labor.

4 0
2 years ago
Lindsay is training two new sales representatives, Lance and Ayden, to use the revised client-tracking database, which has been
Ira Lisetskai [31]

Answer:

The correct answers are lettera "A", "B" and "D": Be sure that Lance and Ayden know how to connect to Lindsay’s desktop; Frequently ask Lance and Ayden if what she is saying makes sense; Expect to review meeting content due to the limitations of virtual technology.

Explanation:

Thanks to technology, training can be given through online platforms that connect individuals even if they are in different parts of the world. Just like in Linday's case. For her training to be successful, <em>Lance and Ayden must interact with Lindsay so she must make sure both of them are connected properly to her desktop.  </em>

<em>After trying the features of the update, Lindsay must make sure both of them are learning and understand what they are doing so asking them if the information provided make sense can help for such a purpose. At the end of the session, Linday has to summarize the content review during the meeting so Lance and Ayden quickly verify what they learned.</em>

7 0
2 years ago
Other questions:
  • As operations manager, you are concerned about being able to meet sales requirements in the coming months. You have just been gi
    8·1 answer
  • San Francisco Corporation uses two materials in the production of its product. The materials, X and Y, have the following standa
    15·1 answer
  • Oscar owns a building that is destroyed in a hurricane. His adjusted basis in the building before the hurricane is $130,000. His
    13·1 answer
  • For a portfolio of 40 randomly selected stocks, which of the following is most likely to be true? a. The beta of the portfolio i
    15·1 answer
  • According to the criterion of _____, a selected segment must be large enough to warrant developing and maintaining a special mar
    14·1 answer
  • Nuthatch Corporation began its operations on September 1 of the current year. Budgeted sales for the first three months of busin
    11·1 answer
  • Two online travel companies, E-Travel and Pricecheck, provide the following selected financial data: ($ in thousands) E-Travel P
    5·1 answer
  • An FI has a $100 million portfolio of six-year Eurodollar bonds that have an 8 percent coupon. The bonds are trading at par and
    5·1 answer
  • Per Chevron’s 3Q 2013 filing, what was the percentage change in the cost of purchased oil products when comparing nine months en
    10·1 answer
  • Shawnee Hospital installs a new parking lot. The paving cost $30,000 and the lights to illuminate the new parking area cost $15,
    11·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!