12

Kahuna Industries has two manufacturing departments--Fabrication and Finishing. The company used the following data at the begin

ning of the year to calculate pre-determined overhead rates:
Fabrication Finishing Total
Estimated total machine-hours (MHs) 4,000 1,000 5,000
Estimated total fixed manufacturing overhead cost $30,000 $3,400 $33,400
Estimated variable manufacturing overhead cost
per machine-hour $2.00 $4.00
During the most recent month, the company started and completed two jobs--Job 14-X and Job 15-Z. There were no beginning inventories. Data concerning those two jobs follow:
Job 14-X Job 15-Z
Direct materials $14,700 $8,400
Direct labor cost $21,600 $8,400
Fabrication machine-hours 2,700 1,300
Finishing machine-hours 400 600
Assume that the company uses a plantwide pre-determined manufacturing overhead rate based on machine-hours. The total manufacturing cost assigned to Job 15-Z is closest to:______.
Business
1 answer:
Morgarella [4.7K]2 years ago
5 0

Answer:

Total manufacturing cost= $34,052

Explanation:

<u>First, we need to calculate the predetermined overhead rate:</u>

Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base

Total estimated overhead= 33,400 + (2*4,000 + 4*1,000)

Total estimated overhead=  $45,400

Predetermined manufacturing overhead rate= 45,400 / 5,000

Predetermined manufacturing overhead rate= $9.08 per machine hour

<u>Now, we can determine the total manufacturing cost of Job 15-Z:</u>

Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base

Allocated MOH= (1,300 + 600)*9.08= $17,252

Total manufacturing cost= 8,400 + 8,400 + 17,252

Total manufacturing cost= $34,052

You might be interested in
Mitsubishi Heavy Industries Ltd. and other Japanese companies manufacture airplanes under license to U.S. firms and also work as
Whitepunk [10]

Answer:

This type of effort is known as <u>collaboration</u>

Explanation:

Collaboration among businesses involve them <u>working together to achieve common business goals which could be </u><u>manufacturing </u><u>or marketing goals.</u>

In such instances, the businesses could combine their resource and share expenses among themselves and this helps reduce costs and increase efficiency.

7 0
2 years ago
Read 2 more answers
The University of Chicago Press is wholly owned by the university. It performs the bulk of its work for other university departm
Sergeu [11.5K]

Answer:

please find the answer below

Explanation:

The University of Chicago

a job costing system involves the process of accumulating information about the costs associated with a specific production or service job service. This information may be required in order to submit the cost information to a customer under a contract where costs are reimbursed.

This involves the accumulation of the costs of materials, labor, and overheads for a specific job.

How to calculate job costing:

Total job cost= direct materials + direct labor + applied overhead

Calculate labor costs:

Determine how much it cost your organization to hire all workers who will work on the project. Multiple the pay per day rate by the number of workers you have estimate to have.

Calculate material costs:

Calculate the cost of all materials that will be used on the job.

Estimate applied overhead:

This is the most difficult to determine, you will need to determine the total overhead costs factoring into the project. This will include your rental expense for the office as well as administrative costs and depreciation of all equipment used.

1. Overview diagram

Indirect Cost Pool    

       

   Cost allocation base  

   Cost Objects: Print jobs  

     

     Direct tracing  

2. Materials Inventory Control    800

Accounts Payable Control       800  

To record purchase of direct materials & supplies

Work-in-Process Inventory Control   710  

Manufacturing Overhead Control   100  

Materials Inventory Control      810

To record direct materials and supplies used

Work-in-Process Inventory Control   1,300

Manufacturing Overhead Control   900  

Wages Payable        2,200  

To record manufacturing labor

Manufacturing Overhead Control   400  

Accumulated Depreciation – Building     400

 and Manufacturing Equipment

To record depreciation of building and manufacturing equipment

Manufacturing Overhead Control   550  

miscellaneous accounts       550  

To record miscellaneous factory overhead

Work-in-Process Inventory Control   2,080  

Applied Manufacturing Overhead      2,080

To assign manufacturing overhead to WIP based on DML dollars

Finished Goods Inventory Control   4,120  

Work-in-Process Inventory Control     4,120  

To record the cost of goods manufactured

Accounts Receivable Control or Cash   8,000  

Sales Revenues        8,000  

To record sales revenue  

Cost of Goods Sold    4,020

Finished Goods Inventory Control     4,020  

To record the costs of the goods sold ($1,300X 160%)

3. T-Accounts:

DIRECT MATERIALS

OPENING BALANCE $100  WORK-IN-PROCESS $710

CASH    $800  

   

WOR-IN-PROCESS

OPENING BALNCE $60  FINISHED GOODS  $4, 120

DIRECT MATERIALS  $710  CLOSING BALANCE  $30

APPLIED MANUFACT- $2, 080

URING OVERHEAD

MAUFACTURING O/H $1, 300        

  $4, 150     $4, 150

FINISHED GOODS

OPENING BALANCE $500  COST OF GOODS SOLD $4, 020

WORK-IN-PROCESS $4, 120  CLOSING BALANCE  $600

  $4, 620     $4, 620

  COST OF GOODS SOLD

FINISHED GOODS $4, 020   PROFIT/LOSS  $4, 020

  MANUFACTURING OVERHHEADS

INVENTORY CONTROL $710   WOR-IN-PROCESS $2, 560

WAGES PAYABLE  $900

ACCUMULATED  $400

DEPRECIATION  

MISCELLANEOUS $550

ACCOUNTS  

  $2, 560       $2, 560

7 0
2 years ago
Read 2 more answers
Assume the Atlas Corporation is expected to pay a $5 cash dividend next year. Dividends are expected to shrink at a rate of 3% p
Simora [160]

Answer: $40

Explanation:

First find the required return using CAPM;

Required return = Riskfree rate + beta * (Market return - riskfree rate)

= 6% + 0.5 * (13% - 6%)

= 9.5%

Then use DDM to determine intrinsic value;

= Next dividend / (Required return - growth rate)

= 5 / (9.5% - (-3%))

= $40

3 0
1 year ago
Why do complex decisions often raise ethical considerations for the entrepreneur?
dlinn [17]
Complex decision often needed to be done by cutting off several corners for the most efficient decision to be enactdd.
For example, during the period when business slowed down, one of the most efficient method to maintain the level of profit is simply by cutting down excessive amount of empployees, but that action is considered unethical
3 0
2 years ago
Hana Coffee Company roasts and packs coffee beans. The process begins by placing coffee beans into the Roasting Department. From
nydimaria [60]

Answer:

Unit Information

Units charged to production:

Inventory in process, July 1                  30000

Received from materials storeroom <u>155000  </u>

Total units accounted for                       185000

<em><u>Units to be assigned costs: </u></em> Equivalent Units

           Whole Units         DM     Conversion

Beginning          30,000    0          27,000

Std and comp  119,000 119,000  119,000

Transferred to  149,000 119,000 146,000

Ending                    36,000  36,000   16,200

Total units         185,000 155,000 162,200

                           Materials Conversion (labor + overhead)

Total costs for the month  620,000 123,272

Total equivalent units      155,000 162,200

Cost per equivalent unit  $4.00       $0.76

                 DM            Conversion           Total

Beginning                                           $121,800.00

Incurred      $620,000.00   $123,272.00  <u> $743,272.00 </u>

Total costs accounted for                             $865,072.00

Beginning             $121,800.00

To complete            <u>   $20,520.00 </u>

Total beginning    $142,320.00

Std and comp        <u>  $566,440.00 </u>

Trasnferred             $708,760.00

Ending                           <u>    $156,312.00 </u>

Total costs assigned       $865,072.00

Explanation:

First we calcualte the physical units.

then the equivalent units.

we solve for equialent cost per unit by dividing the cost of the period by the equivalent unit

then, we make the cost reconciliation

notice how the cost accounted (beginning + incurred during the period)

matches the cost assigned (trasnferred + ending WIP inventory)

4 0
2 years ago
Other questions:
  • Please list any additional qualifications, training, education, skills, or experience that you feel warrant consideration by amc
    12·1 answer
  • (a) Why is one of the men lying in the dumpster?
    12·1 answer
  • Fortune Company's direct materials budget shows the following cost of materials to be purchased for the coming three months: Jan
    15·1 answer
  • When the price of a candy bar is $1.00, the quantity demanded is 500 per day. When the price falls to $0.80, the quantity demand
    11·1 answer
  • The charts that are helpful in making comparisons between categorical variables are a. bar charts and column charts. b. scatter
    8·1 answer
  • The contribution income statement would require a firm to ___________.
    10·1 answer
  • Consider three imaginary countries. In Aire, saving amounts to $4,000 and consumption amounts to $12,000; in Bovina, saving amou
    14·1 answer
  • Some countries have oil as a natural resource and BronzePlate Inc., based in Illinois, is considering building a facility in one
    15·1 answer
  • Which of the following is false regarding the FIFO inventory method?
    13·1 answer
  • Larner Corporation is a diversified manufacturer of industrial goods. The company's activity-based costing system contains the f
    6·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!