Answer:
EOQ = 414 rolls
Explanation:
In order to calculate the number of orders to minimize the cost, we should calculate that by using the Economic order quantity model.
DATA
Holding cost = $1.75/unit
Annual demand = 500 rolls x 12 = 6000 rolls
Ordering cost = $25
Formula
EOQ =
Where
Co = ordering cost
D = Annual demand
Ch = Holding cost
Solution
EOQ = 
EOQ = 
EOQ = 414 rolls
They should order 414 rolls to minimize the cost.
Standard:
Wool required = 2 yard^2 per coat
Cost = $44/ yard^2
Therefore,
Total standard cost per coat = wool per coat * cost per yard squared = 2*44 = $ 88 per coat.
The correct answer is C.
Answer: Decline.
Explanation:
If a million job seekers out of 5 million job seekers, get discouraged and stop job hunting, the unemployment rate would be recorded to have dropped, because it would mean that there are fewer individuals that are seeking for employment( in this case 4million).
Answer:
B. Grouting
Explanation:
These are the options for the question;
A. Epoxy resin
B. Grouting
C. Tensioning
D. Ranging
In the case of dormant cracks wider than about 1m, it is more economical to use grouting method.
Grouting techniques is a techniques that is achieved by removal of dirt or unwanted substance from the crack of the the faulty part and then grouting of the crack after which the surface is sealed by sealants. It should be noted that grouting is economical than other methods such as surface treatment.
Answer:
First, Miguel arrives at an estimate of the total returns that he wants from his investments.
Explanation:
Plato :)