Consider this information about an activity: es = 12, ef = 18, ls = 14, lf = 20. what is the amount of slack associated with thi

s activity?
Business
2 answers:
Effectus [21]2 years ago
6 0

<u>The amount of slack associated with this activity is 2.  </u>

<u />

Further Explanation:

Slack:

Slack is the time period, the activity can be delayed with this limit with completing the project on time. The project should be completed within the timeframe of the project. If one activity is delayed due to any reason, all other activity is delayed. Thus, the whole project is delayed with the time period one activity is delayed.  

The full form of es is the earliest starting time. The full form of ls is the latest starting time. The full form of ef is the earliest finish time. The full form of lf is the latest finish time.  

Given information:

Es = 12

Ef = 18

Lf = 20

Ls = 14

Compute the slack associated with the activity:

The slack is computed by two methods. One method of calculating the slack is taking the difference of the earliest starting time and the latest starting time. Another method of calculating the slack is taking the difference of the earliest finish time and the latest finish time.

Slack= Latest finish time – Earliest finish time

        =  20 – 18

        = 2

Slack= Latest starting time – Earliest starting time

        =  14 – 12

        = 2  

Therefore, the activity can be delayed for 2 days, if the activity is delayed for more than 2 days. The project is not completed on time.  

Learn more:

1. Learn more about egg viability hypothesis

<u>brainly.com/question/7184325 </u>

2. Learn more about organizing data

<u>brainly.com/question/9824390 </u>

3. Learn more about hypothesis

<u>brainly.com/question/1579945 </u>

<u> </u>

Answer details:

Grade: Middle School

Subject: Business

Chapter: Project completion  

Keywords: amount of slack, associated, can be delayed, with this limit, with completing the project, computed, earliest finish time and the latest finish time, earliest starting time and the latest starting time.  

Julli [10]2 years ago
3 0
<span>The slack can easily be explained as the difference between latest start (ls) and earliest start (es) of an activity. As the above example, we can easily now calculate slack as the follow: slack = LS - ES or LF - EF So, the correct answer will be LS - ES = 14 -12 = 2 or LF - EF = 20-18 = 2 So, the slack associated with this activity is 2.</span>
You might be interested in
A colleague from the plant in Germany has arrived at the Chicago plant to share insights on a recent product line changeover imp
tester [92]

Answer: jim already had a rigid opinion about what will work in the United States .

Superiority complex on the side of Jim.

Language barrier.

He is not impressed by the German outlook and dressing

Explanation:there are several barriers that may hinder the successful implementation of the new product line which has saved thousand of euros for the Germans,one is the fact that Mr jim already has a predisposed idea that the implementation will not work one can only wonder why he invited the German in the first place,it's obvious that the invitation if the German came from a higher pedestal and could be one if the reason Mr jim believes contrarily ,he believes innovation will not work in the USA,meanwhile ,world over , workers tend to resist change and innovation but there are a lot of measures to bring them to the table which include engaging them in every stageof the implementation , assuring them that there will be no job loss due to innovation,making them to see the advantages of the proposed changes to all.

The feeling of superiority to the Germans and their technology is very obvious ,ranging from the quiet disparaging of the visitors accent and pronounciation ,condemn his outfit rather than concentrating on what he has to offer ,he has a set mind ,which find everything about the Germans repulsive.it will be difficult to adopt the new technology with Jim at the helm of affairs at the Chicago plant .

7 0
1 year ago
Whistle works sells each whistle for $12. They have a desired ending inventory for production of 20% of the next months budgeted
Ksivusya [100]
This question needs more information.
3 0
2 years ago
ane is planning to offer a Groupon for inner tube rentals that she will distribute on hot, sunny, summer days by the river that
sweet [91]

Probability assigned:|

x 30 60 120 180

P(x) .10 .40 .40 .10

Answer:

Jane

Price of Groupon for a revenue of $300 is:

$3

Explanation:

a) Data and Calculations:

Expected Sales volume:

Number of Tubes  x   30     60      120     180

Probability P(x)           .10     .40      .40      .10

Expected values          3      24       48       18

Total = 93 tubes

Groupon price = $300/93 = $3.23

b) Jane's price for each Groupon will be the rent revenue per day divided by the expected number of tubes to rent daily.  The expected number of tubes is derived by multiplying each expected number of tubes by its probability and then summing up the results.

6 0
1 year ago
The Distribution Point plans to save $2,000 a month for the next 3 years for future emergencies. The interest rate is 4.5 percen
ch4aika [34]

Answer:

A deposit of 36,922.02 dollars will be equivalent to the series of emergencies deposits of 2,000 starting today.

Explanation:

we need to know the future value of the emergencies deposit and then, calculate which lump sum can generate the same amount. As the deposit are done at the beginning It will be an annuity-due:

C \times \frac{(1+r)^{time} -1}{rate}(1+r) = FV\\

C 2,000

time      36 (3 years x 12 months per year)

rate 0.045

2000 \times \frac{(1+0.045)^{36} -1 }{0.045}(1+0.045) = FV\\

FV $180,082.6885

Now we calculate the lump sum which yield this amount as well:

\frac{Maturity}{(1 + rate)^{time} } = PV  

Maturity  $180,082.6885

time   36.00

rate  0.045

\frac{180082.68854409}{(1 + 0.045)^{36} } = PV  

PV   36,922.02

5 0
1 year ago
Who determines who is authorized for access to areas containing sensitive devices/data/system
Alex Ar [27]

Answer:

Im thinking it is the FBI

Explanation: MY guess would point to the FBI bc they are the ones who come in on cyber related crimes. so i would say A is the correct answer

6 0
2 years ago
Read 2 more answers
Other questions:
  • Stan has made a $125.30 monthly deposit into an account that pays 1.5% interest, compounded monthly, for 35 years. He would now
    8·1 answer
  • Blue Ice Inc. is an American corporation. The company started out as a _____ between Nick Selver and Rita Andrew in 1985. In 200
    8·2 answers
  • The Ruff Jeans Company produces two different types of jeans, Simple Life, and Fancy Life. The company sales budget estimates th
    14·1 answer
  • Mike used to work as a commercial painter for $40,000 per year but quit in order to start his own painting business. To invest i
    6·1 answer
  • Lithium, Inc. is considering two mutually exclusive projecLithium, Inc. is considering two mutually exclusive projects, A and B.
    12·1 answer
  • Ten years ago, John purchased a deferred annuity and named his daughter, Suzanne, as beneficiary. Over the years, John invested
    7·2 answers
  • Northern Trail Outfitters has released a Customer Service Community for its users and trekking equipment. Users can ask and answ
    11·1 answer
  • Les is concerned that his variable cost per unit projection for a project may not be reliable. Which type of analysis will best
    12·1 answer
  • Define what the book value of an asset is by choosing the correct statement(s) below. (Check all that apply.) Multiple select qu
    8·1 answer
  • You have 21 product displays. Six have 5 shelves and 15 have 4 shelves. It is store policy to dedicate at least one full shelf t
    12·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!