Answer:
The total overhead variance in hours taken is 3,600 hours
The total overhead cost variance is $1,110
Explanation:
The variance is about the different between budget/ standard and actual figures.
Standard hours allowed for the work done is 22,200 hours; and the predetermined overhead rate is $5.75 per direct labor hour. So total cost budgeted for work done is $127,650 = $5.57 x 22,200 hours
The total overhead variance in hours taken = standard hours of 22,200 - actual direct labor hours of 18,600 = 3,600 hours
The total overhead cost variance = standard cost - actual cost = $127,650 - $126,540 = $1,110
When a government introduces regulations addressing worker safety and environmental protection, it affects businesses and consumers.Businesses face Higher cost because the must alter existing infrastructure to<span> meet regulations. As a result, consumers pay more for the same produced goods.
Hope this helps!</span>
<h2>Answer:</h2><h3>To me i think that the answer is e) ad analysis </h3><h2>Explanation:</h2><h3>she was going around and survey a sample group of people. Then she suggested to her company about they develop a customizable travel application.</h3>
Answer:
The likely outcoe could be,
Likely be:
- Glinda will win, because the statute of limitations starts to run on the date, she filed a suit, i.e. Feb.22, 2014.
- Glinda will win, because the statute of limitations starts to run from the time that the she discovered the breach, i.e. Jan. 17, 2014.
Likely not be:
- Glinda will lose, because the statute of limitations ran on Jan. 13, 2013, i.e. two years after the date the contract was entered on Jan. 14, 2011.
-Glinda will lose, because the statute of limitations requires a demonstration of attempt to cure.