Answer:
The correct answer is A. late start date.
Explanation:
The slack of the Project is the margin of movement that the Project has. It will allow us to know where and when the Project may be at risk of impact and implement the appropriate measures
.
- Total Project Slack: is the amount of time a Project activity can be delayed without delaying the Project end date.
- Project Free Slack: The amount of time that a Project activity can be delayed without delaying its successor's early start date.
- The Project slack: is the time that a Project can be delayed without delaying the deadline imposed for its completion.
- Positive slack: late dates are greater than early, time frame beyond the early end to conclude the activity.
- Negative slack: late dates will be less than early, indicating a delay from the scheduled end.
- Zero Slack: the early and late dates for each activity are the same, this implies that the activity is critical, it belongs to the critical path of the Project.
Answer:
c. criterion deficiency
Explanation:
Based on the information provided within the question it can be said that in this scenario it seems that the performance management system suffers from Criterion deficiency. This term refers to a company failing to assess one or more very important aspects of the process of job performance appraisal for employees within the company. Such as is the case in this scenario as the company is only looking at the sales revenue and completely ignoring all of the other important factors.
Answer: d. $6,500.
Explanation:
The question makes it seem quite complicated but it's not. In calculating the amount Trell will receive from the factor we do the following,
We take the fair value of Trell's 20% interest of $8,000 and subtract the factoring fee from it.
The factoring fee is,
= 50,000 * 3%
= $1,500
Subtracting it we have,
= 8,000 - 1,500
= $6,500.
Trell will show an amount receivable from factor of $6,500 so option D is correct.
Answer:
at the time it receives a negotiable warehouse receipt for the bats.
Explanation:
Benson Bearing Company is selling bats to Textron inc. The bats are stored at an independent warehouse not controlled by Benson Company.
Of the contract states that Textron will pick up the bats at the warehouse, the risk of loss passes to Textron when it recieved a negotiable warehouse reciept for the bats.
This is because the warehouse is not controlled by Benson Company and issuing a warehouse reciept is equivalent to delivering the goods to Textron.
Answer:
Forecast exchange rate = $2.29(Approx)
Explanation:
Given:
Exchange rate = $1.95
Inflation rate difference = 2.6% - 20% = 17.4%
Computation:
Forecast exchange rate = 1.95 / (1-17.4%)
Forecast exchange rate = $2.29(Approx)