Answer:
Please kindly go through explanation for the answers.
Explanation:
A)The required return if Beta is 2 = 0.06+0.08*2 =0.22
B)Here Rf = 0.06
Expected return of the portfolio = 0.4*22% + 0.6*6% =12.4%
since beta of Rf = 0,the expected beta = 0.4*2 = 0.8
C)Beta is nothing but systematic risk of a security in comparing to the market. In this case stock z having beta of 1.5 which is less than beta of stockX i.e 2. and expected return is 15%.so stockz is offering lower return at lower risk. If the investor is a risk averse its a good buy.
D) let W be portion of stock X.
Then w*2 + (1-w)*0 = 1.5
W = 1.5/2 =0.75
to construct a portfolio which has a beta of 1.5 we have to invest 75% of our money in stock X and remaining in risk free asset
E) expected return = 0.22*.75 +0.25*0.06 = 16.5% + 1.5% = 18%
Answer:
The correct option is C.
Explanation: Price elasticity is the measure of the rate of change in the level of quantity demanded due to a change in the level of price.
Price elasticity is usually negative, this means that it follows the law of demand; as price increases quantity demanded decreases.
Also, another incidence that can affect price elasticity is an availability of cheaper alternatives. If cheaper alternatives of a particular product are introduced into the market, the demand for that product will reduce, because consumers will abandon it for its cheaper alternatives, thereby driving the elasticity of that product higher.
Therefore, in the scenario given above, the elasticity is higher than -1.2 because there are new brands that have just been introduced into the market.
Answer: <u>The correct answer is D).</u>
<u />
Explanation: A blue ocean strategy is used to gain a broad and durable competitive advantage by abandoning existing markets and inventing a new market segment in which competitors are minimal and allow the company to meet a new demand.
Answer: Your Advisor
Explanation:
MyUC / UC One is a portal for UC students.
Answer:
(a) The Vasquez construction is the principal, the surety is the party that underwrites the contract and local school board is the obligee.
(b) If Vasquez fails to finish the contract, then the surety will be required to pay for the loss suffered by the obligee due to the contract failure.
(c) In a surety bonds contract, the surety has a legal right to get back the losses from the principal.
Explanation:
Solution:
(a) Under a performance bond contract, the owners assures that the work will be completed within a specific time frame and contract specification.
In this example given, the Vasquez construction is the principal, the surety is the party that underwrites the contract and local school board is the obligee.
(b) If the Vasquez construction fails to complete or finish the contract, then the surety will be obliged to pay for the loss suffered by the obligee due to the failure of the contract.
(c) In a surety bond contract, the surety has a legal right to recover the losses from the principal. for this later on, the surety can recover it's loss from the principal.