Answer:
Correct option is E.
<u>14 pesos per dollar</u>
Explanation:
The exchange rate between Mexican pesos and dollars was 13.5 pesos per dollar.
According to the relative Purchasing Power Parity (PPP), the exchange rate was in equilibrium. But now,
Mexican inflation = 10%
U.S inflation = 3%
Now the Mexican peso is overvalued by = 10% - 3% = 7%
So, the possible increase in exchange rate (of pesos per dollar) considered with this assertion is = Exchange rate of pesos per dollar * Inflation rate
= 13.5 * 7%
= 13.5 * 7/100
= 0.945
The possible in exchange rate = Previous Exchange rate + Increase in exchange rate
= 13.5 + 0.945
= 14.445
= 14.4 (rounding off)
=14
Answer
Increase- a popular new diet prescribes
only olive oil for weight loss
Increase- a report in news stating that
consumption of olive oil
improves health
Decrease- a decrease in the price
of other vegetable oil
Decrease- research shows that olive oil
consumption leads to hair loss
Explanation:
Answer: $153,782.70
Explanation:
The MACRS allowance percentages are as follows, commencing with Year 1: 14.29, 24.49, 17.49, 12.49, 8.93, 8.92, 8.93, and 4.46 percent.
In 4 years, the depreciation would be:
= Cost price * (4 year deprecation)
= 525,000 * (14.29% + 24.49% + 17.49% + 12.49%)
= $360,990
Book value :
= 525,000 - 360,990
= $164,010
Gain (loss) = Sale price - Book value
= 150,000 - 164,010
= ($14,010)
Tax payable = (14,010) * 27%
= ($3,782.70)
After-tax cash flow:
= Selling price - Taxes
= 150,000 - (-3,782.70)
= $153,782.70
<em>Note: If there are options, beware of rounding errors and pick nearest option. </em>
Answer:
Total slack
Explanation:
Total slack is defines as the time that tasks are delayed which will eventually affect the finishing date of a project.
Total slack can be either positive or negative. Positive slack is when delay in tasks do not affect project finish date, and negative slack are delays that affect project finish date.
Total slack is calculated as difference between smaller value of late finish and early finish.
Tom shares 4 days of his slack with the contractor.
So he has 10- 4 = 6 days slack
The total slack is 6 + 4= 10 days
In this scenario the difference between late start and early start is 9 - 5= 4 days
Based on the information given the amount of the transfer taxes is $476.
Using this formula
Total transfer tax=[(Purchased price+ First transfer tax)×(Additional tax)]+Transfer tax
Let plug in the formula
Total transfer tax=[($475,000-$1,000)×($0.10/$100)]+$2
Total transfer tax = ([$474,000 x .001] + $2)
Total transfer tax=$474+$2
Total transfer tax=$476
Inconclusion the amount of the transfer taxes is $476.
Learn more here:brainly.com/question/17122829