Wildhorse Construction Company had a contract starting April 2021, to construct a $24900000 building that is expected to be comp

leted in September 2023, at an estimated cost of $22900000. At the end of 2021, the costs to date were $12595000 and the estimated total costs to complete had not changed. The progress billings during 2015 were $3,600,000 and the cash collected during 2015 was $2,400,000.
At December 31,2015 Cooper would report construction in process in the amount of:_______?
Business
1 answer:
jek_recluse [69]2 years ago
3 0

Answer:

The construction in process amount reported at December 2021 is $13,695,000

Explanation:

In this question, we are asked to state the amount the company will report construction in the process of.

Firstly, we calculate the profit = Total contract price - Expected costs of contract = $24,900,000-$22,900,000 = $2,000,000

The profit in percentage of cost is; 2,000,000/22,900,000 = 8.73%

The costs incurred in 2021 is $12,595,000

The proportionate profit = 12,595,000 * 8.73 = $1,100,000

The construction in process at December 2021 = Cost incurred + Proportionate profit = 12,595,000 + 1,100,000 = $13,695,000

You might be interested in
According to the overall staffing organizations model, hr and staffing strategy are driven by ______________.
alexandr1967 [171]
The staffing organizations model are driven by staffing stradegy!!!
love sent from the district of columbia! <3333
8 0
1 year ago
Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into three acti
adell [148]

Answer:

1. schedule variance = -$52,500

2. SPI = 0.65

3. CPI = 0.56

Explanation:

to get the solution, we calculate for BRWS and BRWP

first we calculate the budgeted revenue of the work scheduled for each activity using this formula:

<u>budgeted</u><u> </u><u>revenue</u><u> </u><u>*</u><u> </u><u>planned</u><u> </u><u>completion</u>

A = 25,000 x 100percent

= $25000

B = 150,000 x (25/30) percent

= $125000

C = 50000 x 0percent

= 0$

total = $25000+$125000+$0

= $150000

Next we calculate budgeted revenue of work performed (brwp)

<em>calculated using this formula</em>:

<u>budgeted revenue x actual </u><u>completion</u>

A = 25000 x 90percent

= 22500 dollars

B = 150000 x 50percent

= $75000

C = 50000 x 0%

= $0

total = 22500 + 75000 + 0

= $97500

<u>1</u><u>.</u><u> </u><u>schedule</u><u> variance</u><u> </u><u>=</u><u> </u><u>BRWP </u><u>-</u><u> </u><u>BRWS</u>

<u>=</u><u> </u>$97500 - $150000

= -$52500

<em>we </em><em>have</em><em> a</em><em> </em><em>negative</em><em> </em><em>schedule</em><em>,</em><em> </em><em>telling</em><em> </em><em>us </em><em>that </em><em>the </em><em>project</em><em> </em><em>is </em><em>behind</em><em> </em><em>schedule</em>

<em>2</em><em>.</em><em> </em><u>schedule</u><u> </u><u>performance</u><u> </u><u>index </u><u>=</u><u> </u><u>revenue</u><u> </u><u>of </u><u>work </u><u>performed</u><u> </u><u>divided </u><u>by </u><u>revenue</u><u> of</u><u> work</u><u> </u><u>schedule</u>

<u>=</u><u> </u>97500/150000

= 0.65

3. <u>cost price index = revenue of work performed divided by actual revenue</u>

= 97500/175000

= 0.56

4. <u>how </u><u>the </u><u>project</u><u> </u><u>is </u><u>going</u><u>:</u>

the schedule performance index (SPI) is 0.65 which is less than 1. this is to say that the project is doing better than planned revenue when we talk of revenue

4 0
1 year ago
Which action best reflects the influence of John Maynard Keynes? O A. A business lobbies a government to reduce its overall tax
Sidana [21]

Answer:

Which action best reflects the influence of John Maynard Keynes?

B. A government gives jobs to workers during an economic recession.

Explanation:

John Maynard Keynes was a The British economist who strongly and vehemently advocated for "increased government expenditures, lower taxes, government offering full employment, and government intervention in economic activities" in order to stimulate demand, pull the economy out of recession, and kickstart it from slump.  He is known as the father of Keynesian Economics.

8 0
1 year ago
A company’s stock is currently selling for 28.50. Its next dividend, payable one year from now, is expected to be 0.50 per share
melisa1 [442]

Answer: $22.22

Explanation:

We can use the dividend discount model to solve for this.

The formula is,

P = D1 / r - g

Where,

D1 = the next dividend

r = the expected return

g = the growth rate.

We do not have the expected return but we can calculate for it using the old stock price and growth rate. Making it x we have,

28.5 = 0.5 / x - 0.075

28.5 (x - 0.075) = 0.5

x = 0.5 / 28.5 + 0.075

x = 0.09254385964

x = 9.25 %

Now that we have the expected return we can calculate the new stock price with the new growth rate,

P = 0.5 / 9.25% - 7%

P = 22.2222222222

P = $22.22

The new stock price is $22.22

5 0
1 year ago
Nachman Industries just paid a dividend of D0 = $1.32. Analysts expect the company's dividend to grow by 30% this year, by 10% i
ladessa [460]

Answer:

$44.87

Explanation:

Use Dividend Discount Model to solve this question;

First, find the dividend per year;

First year's dividend ; D1 = D0(1+g)

D1 = 1.32 (1.30) = 1.716

Second year's dividend ; D2 = 1.716 (1.10) = 1.8876

Third year's dividend ; D3 = 1.8876 (1.05) = 1.9820

Next, find the present value of each dividend at 9% required return;

PV (D1) = 1.716 / (1.09) = <em>1.5743</em>

PV (D2) = 1.8876 /(1.09²) = <em>1.5888</em>

PV (D3 onwards) = \frac{\frac{1.9820}{0.09-0.05} }{1.09^{2} } \\ \\ = \frac{47.19}{1.1881}

= PV (D3 onwards) = <em>41.7052</em>

Sum up the PVs to find the current market value of the stock;

= 1.5743 + 1.5888 + 41.7052

= 44.8683

Therefore the value is $44.87

5 0
1 year ago
Other questions:
  • The latest demand equation for your Banjos Rock T-shirts is given by q = −30x + 7200 where q is the number of shirts you can sel
    7·1 answer
  • Suppose the price of a Snickers candy bar is $2.00 at both the airport and the grocery store. The price elasticity of demand for
    5·2 answers
  • Credit in developing countries can be granted through formal or informal channels. Formal channels include institutions such as
    9·1 answer
  • Matthew is an accountant at Larson Enterprises. He frequently feels pressured to make unethical accounting decisions in order to
    6·1 answer
  • Tina's Track Supply's market-to-book ratio is currently 4.5 times and PE ratio is 10.5 times. If Tina's Track Supply's common st
    12·1 answer
  • The typical consumer's food basket in the base year 2015 is as follows: 30 chickens at $4 each 10 hams at $5 each 10 steaks at $
    9·1 answer
  • Lucas Corporation uses the weighted-average method in its process costing system. Data concerning the first processing departmen
    6·1 answer
  • On the first day of the fiscal year, Shiller Company borrowed $63,000 by giving a five-year, 12% installment note to Soros Bank.
    7·1 answer
  • Games R Us manufactures various games. For March, there were no beginning inventories of direct materials and no beginning or en
    8·1 answer
  • The following information applies to the questions displayed below.] Pastina Company sells various types of pasta to grocery cha
    13·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!