Answer:
It should be accepted as the cash flow is greater than minimum
Explanation:
We should determinate if he project can generate a cashflow of 151,406 after taxes to be accepted:
market x market share = sales in units
140,000 units x 8.5% = 11,900 units
sales x contribution less fixed cost = income before taxes
11,900 x 56.11 - 387,200= 280,509
after tax 280,509 x (1 - 21%) = 221,602.11
project cash flow > minimum cash flow
221,602.11 > 151,406
It should be accepted as the cash flow is greater than minimum
Answer:
power source, motor type , motor connection, and environment and controller
Explanation:
when we install motor control system
there are many factor which we consider while installing and they are as
- power source that is need for operate machine
- motor type that is depend on our work output
- motor connection need horse power and service factor etc
- environment that is also important for outside of equipment with dust and moisture etc
- controller type it is depend upon type of motor and its purpose
so these are some type of factor which we consider while installing
Answer:
PV of lease annuity is $25000
Explanation:
As the paymengt will be made at the end of the year, the annuity is an ordinary annuity. We will calculate the present value of the ordinary annuity using the following formula,
PV Annuity = PMT * [( 1 - (1+r)^-n) / r]
Where,
- PMT is periodic payment
- r is discount rate per peiod
- n is number of periods
Thus,
PV of annuity = 3895.5 * [( 1 - (1+0.09)^-10) / 0.09]
PV of annuity = $24999.985 rounded off to $25000
Answer:
c. increases
Explanation:
Opportunity cost is the cost of the next best option forgone when one alternative is chosen over other alternatives.
The production possibility frontier is graph that shows the two combinations of goods that an economy can produce given its resocurces.
As the production of donuts increases, the amount of beers that would be forgone in order to increase production of donuts rises.
I hope my answer helps you
Answer:
Min 2M + 3B
Explanation:
Data provided in the question
Let us assume M denotes the making units
B denotes the buying units
So,
Making cost per unit = $2
And, the buying cost per unit = $3
And, the total number of units required = 4,000 units
Based on the above information, the objective function is Min 2M + 3B.
This indicates the minimum total cost
Hence, the correct option is A.