<span>A.) Jessica is low risk and will pay her outstanding balances on time.</span>
Answer: D) Favorable Unfavorable
Explanation:
To begin, it is worthy of note that in Variance, if something is said to be Favourable, it means a negative Variance because less resources than planned were spent. When it is Unfavourable, it means a positive balance variance.
Now, The formula for Labour Rate Variance is as follows,
LABOUR RATE VARIANCE=(ACTUAL RATE-STANDARD RATE)*ACTUAL HOURS WORKED
Seeing as the old workers were being paid $18, and the new office ones were paid $10, we can see that to be the actual rate was less than the standard rate. This would mean that there was a FAVOURABLE balance.
Labour Efficiency is calculated in a similar way,
LABOUR EFFICIENCY VARIANCE=(ACTUAL HOURS WORKED-STANDARD HOURS)*STANDARD RATE.
Now, these are Office workers not assemblyline workers. They do not have the experience to work in such a way that they produce as fast or as efficiently as their striking Assemblyline colleagues.
This would then mean that their actual hours will be MORE than the standard rate which can only lead to an UNFAVOURABLE BALANCE.
Answer:
We should calculate this using the safety stock formula Z x standard deviation x Lead time
Explanation:
ired = 90%
For 90% service level the value of Z (standardized normal distribution table) = 1.281
Z is found in standard normal distribution table.
Find value of 0.45 (0.9/2) in the table and note row and column values.
Answer:
The correct answer is Transparency.
Explanation:
Within the scope of ethical values, Transparency is known as the capacity that a human being has for others to clearly understand their motivations, intentions and objectives. Similarly, Transparency focuses on carrying out practices and methods available to the public, without having anything to hide.
Answer:
Part A:
Labur Productivity:
For US=5.14, LDC=1.35
Capital Productivity:
For US=1.72 LDC=4.31
Part B:(Multi factor productivity)
For US=1.29 LDC=1.03
Part C: (Raw material productivity)
For US=4.90 LDC=10.02
Explanation:
Part A:
Labur Productivity:
For US:

For LDC:

Capital Productivity:
For US:

For LDC:

Part B:
For US:

For LDC:

Part C:
For US:

ForLDC:
Converting Raw material FC into $ (1$=10FC)
Raw Material =19550/10=$1955
