Answer:
8 hours
Step-by-step explanation:
Job v starts at time 0 and completes at time 3.
Job w starts at time 1 and completes at time 4.
Job x starts at time 4 and completes at time 8.
Job y starts at time 8 and completes at time 10.
Job z starts at time 10 and completes at time 15.
The average completion time is (3 +4 +8 +10 +15)/5 = 8 . . . hours.
_____
<em>Comment on the schedule</em>
Jobs v and x are the only ones completed by the time due. The latest is 8 hours late. If they are scheduled in order of due time, jobs v, w, and y can be completed by the due time; the others will be 4 and 6 hours late.
Answer:
First person: $107
Second person: $98
Third person: $93
Step-by-step explanation:
Let be "f" the amount of money (in dollars) that the first person contributed to the purchase, "s" the amount of money (in dollars) that the second person contributed to the purchase and "t" the amount of money (in dollars) that the third person contributed to the purchase.
With the information given in the exercise, you can set up the following equations:
Equation 1 → 
Equation 2 → 
Equation 3 → 
Substitute the Equations 2 and 3 into the Equation 1 and then solve for "f":

Finally, substitute the value of "f" into the Equation 2 and then into the Equation 3, in order to find the values of "s" and "t".
Therefore, you get:

Answer: A - Ahmed wins the chess game
Step-by-step explanation: