Answer: $11,200
Explanation:
Using the accounting equation:
(Total Assets) = (Total Liabilities) + (Total Capital)
So,
(Total Liabilities) = (Total Assets) - (Total Capital) (1)
Based on equation (1), in order to compute for the total liability, we need to compute the total assets and total capital.
At the end of the first year, the following are the assets Shapiro's consulting services (together with the amount):
Cash: $16,000
Office Supplies: $3,200
Equipment: $24,000
Accounts Receivable: $8,000
TOTAL ASSETS $51,200
Note that the total assets is obtained by adding the amount (or value) of the all the assets listed above.
Since the net income is an increase (or decrease if it's a net loss) of capital, we classify net income as capital. In particular, the net income of Shairo's at the end of first year adds to the capital at the start of first year.
Moreover, the withdrawal of money by the owner also decreases the capital.
Thus, the total capital at the end of first year is calculated as follows:
Capital (start of the year): $15,000
Net Income (end of year): $27,000
Withdrawal Amount: ($2,000)
TOTAL CAPITAL: $40,000
Note: ($2,000) means -$2,000. This notation is used in accounting.
Hence using equation (1), the total liabilities at the end of first year is given by
(Total Liabilities) = (Total Assets) - (Total Capital)
= $51,200 - $40,000
Total Liabilities = $11,200
Answer:
Projects Y and Z
b. Projects W and Z
c. Projects W and Y
Explanation:
CAPM equation : Expected return = Risk free rate + Beta x (Expected market return - Risk free rate)
W = 4% + [0.85 x (11% - 4%)] = 9.95%
X = 4% + (0.92 x 7%) = 10.44%
Y = 4% + (1.09 x 7%) = 11.63%
Z = 4% + (1.35 x 7%) = 13.45%
Projects Y and Z have an expected return greater than 11%
b. Projects W and Z should be accepted because its expected return is higher than the IRR
c. Project W would be incorrectly rejected because the expected rate of return is less than the overall cost of capital (i.e. 9.95 is less than 11). But its expected rate of return is greater than the IRR
Y would be incorrectly accepted because its expected rate of return is greater than the overall cost of capital but its expected rate of return is less than the IRR
Answer: $1,227
Explanation:
The value of the futures contract should be calculated by the formula;
= Stock Index Value * ( 1 + risk free rate ) - dividends
= 1,200 * ( 1 + 0.06) - 45
= $1,227
Answer:
Marnie will save = $ 125 from her raise .
Explanation:
raise income = $500
MPC = = 0.75
Marnie consumer 0.75 of every dollar increase . So total consumption increase = 500 * 0.75 = 375 $
Marnie will save = 500 - 375 = $ 125 from her raise .
Answer:
The firm average total cost is $110
correct option is d. $110
Explanation:
given data
total fixed costs = $300,000 per year
average variable cost = $80
tents = 10,000
to find out
we know that average total costs is sum of average fixed cost and average variable cost .........................1
here
Average fixed cost = total fixed cost ÷ number of unit output
Average fixed cost = 
Average fixed cost = $30
so
average total costs = Average fixed cost + average variable cost
average total costs = $30 + $80
average total costs = $110
correct option is d. $110