Answer:
In order to make 45 brownies, Abel needs 25 cups of flour, 20 cups of sugar, 10 cups of cocoa powder and 5 eggs.
Step-by-step explanation:
As the recipe is missing in this question, the recipe is found online which given following information
- Abel needs 5 cups of flour to make brownies.
- If Abel uses 4 cups of sugar.
- he will need to use 2 cups of cocoa powder.
- The recipe will make brownies if Abel uses only 1 egg.
Abel has to make 45 brownies for the sale, this is also missing in this question, however is given in the reference question linked here.
This recipe is to make 9 brownies. Now for 45 brownies the multiplier is found as 45/9=5. So by multiplying quantity of all the ingredients by 5, Abel will be able to make 45 brownies.
Now in order to make 45 brownies
- Abel needs 5*5 =25 cups of flour to make brownies.
- If Abel uses 5*4=20 cups of sugar.
- he will need to use 5*2=10 cups of cocoa powder.
- The recipe will make brownies if Abel uses only 5*1=5 egg.
So in order to make 45 brownies, Abel needs 25 cups of flour, 20 cups of sugar, 10 cups of cocoa powder and 5 eggs.
Answer:
736 N
Step-by-step explanation:
The dimensions of the rectangular tile are:
Length = 2.3m
Width = 1.6m
The pressure exerted on a surface is given by the formula

where
p is the pressure
F is the force exerted
A is the area on which the force is exerted
In this problem, we have:
is the maximum pressure that the tile is able to sustain
A is the area of the tile, which can be calculated as the product between length and width, so:

Re-arranging the formula for F, we can find the maximum force that can be safely applied to the tile:

To answer this question, an assumption must be made, that Eva spends 8 hours a day working. If this is the case, then Eva will complete jobs w, x, and v on day one, for a total of six hours. Since the next job (y) requires 4 hours, she will spend two hours working that day, leaving 2 more hours to go on that job. The next day she will spend 2 hours finishing job y, completing it, and finish the longest job z (hours) that day. This means she had 4 jobs on day one, and 2 jobs on day 2 for and average of 3 jobs per day.
This answer assumes an 8 hour work day, and that Eva can start a job she cannot finish that day.
Expected Mean, E(X), is obtained by multiplying each pair of

and its

and add up the answers
E(X) = (0×0.7) + (1×0.2) + (2×0.1) = 0.4
The formula to calculate the variance, Var(X), is given by E(X)² - (E(X))²
E(X²) = (0²×0.7) + (1²×0.2) + (2²×0.1) = 0+0.2+0.4 = 0.6
(E(X))² = (0.4)² = 0.16
Var(X) = 0.6 - 0.16 = 0.44
Translating these answers into the context we have
E(Y) = 0.4×500 = $200
Var(Y) = $110
Answer:
(5x²+2y² + 2xy)(5x²+2y²-2xy)
Step-by-step explanation:
25x⁴+4x²y²+4y⁴= (5x²)²+2*5x²*2y²+(2y²)² - 16x²y²= (5x²+2y²)² - (4xy)²= (5x²+2y² + 2xy)(5x²+2y² - 2xy)