Answer:
The correct answer is letter "A": Respect.
Explanation:
The Project Management Institute or PMI is an American non-profit organization that defines and keeps standards for project management within organizations. According to the PMI, the values for ethical project management involve responsibility, fairness, respect, and honesty. Respect implies showing high awareness for managers, others involved in the firms, and the resources provided to the executives.
Answer:
The correct answer is option (A) $42.00
Explanation:
Solution
Given that:
The established rate is given as = 100,000/40,000
= $2.5 per hour
Thus
The cost of the job is shown is shown below:
The direct material = $5,000
The direct labor = $2400
Then
The manufacturing overheard is = 400 * 2.5 = $1,000
So,
The total cost is = $5,000 + $2400 + $1000 = $8,400
To get our unit cost,
Unit cost = $8400/200 = $42.00
It is important to know that, the number of labor hours used in jobs = Total labor cost/Rate per hour
=2,400/6 = 400 hours
The price of corn will increase will definitely occur in the corn market.
Option A
<u>Explanation:
</u>
Ethanol is a renewable fuel of several organic materials known as "biomass." Further, then 98% of U.S. petroleum includes ethanol, usually E10 to control air emissions, or E10 (10% ethanol, 90% gasoline). Oxygenation of petrol
Corn ethanol is the primary ethanol origin of ethanol fuel throughout the United States derived from corn biomass.
Maize ethanol is generated by fermenting and distilling of ethanol. It is questionable whether corn ethanol consumption leads to lower pollution of greenhouse gas than petrol.
Answer: 99.51%
Explanation:
This is a linear regression problem.
The relationship between the success of the team and the occupancy rate is in the form:
y = mx + c
y = occupancy rate
m = slope
x = number of games
c = slope
Intercept is supposed to be negative in question:
= 0.0474 * 31 + (-0.4743)
= 99.51%
<em>Options are most probably for a variant of this question.</em>
Answer:
3,825.2 labor hours
Explanation:
Learning rate (Unit 1 and unit 2):
= Labor hour required for 2nd unit ÷ Labor hour required for 1st unit
= 1,200 ÷ 2,000
= 0.60
Learning rate (Unit 2 and unit 3):
= Labor hour required for 3rd unit ÷ Labor hour required for 2nd unit
= 1,130 ÷ 1,200
= 0.94
Average of learning rates = (0.60 + 0.94 ) ÷ 2
= 0.77
As per learning curve calculator the value of 77% for 6 units = 4.0776
Cumulative time = Factor × Time of first unit
= 4.0776 × 2,000
= 8,155.2
Hence,
Time for next three units:
= Cumulative time - Sum of the time of first, second and third unit
= 8,155.2 - (2,000 + 1,200 + 1,130)
= 3,825.2 labor hours should Simpson plan for.