Standard deviations of the four activities of the critical path are 1,2,4,2.
Standard deviation of this critical path = Sum of square root of variance of this corresponding critical path
Standard deviation of critical path 



Now we need to find the probability that the project will completed in 38 weeks given that its expected completion time is 40 weeks.
That is, we need to find P(X<38) :


Probability 
Thus the probability that the project will be completed in 38 weeks is 0.34.
From 0g to 494.7g are rejected as well as those heavier than 505.3grams.
You calculate this by subtracting and adding 5.3 to 500
The side of the congruent side of the triangle should be greater than 7 feet.
Answer:
Option C is correct.
Ratio of longer leg to hypotenuse is; 
Step-by-step explanation:
This is the special right angle triangle 30°-60°-90° as shown below in the figure.
- The side opposite the 30° angle is always the shortest because 30 degrees is the smallest angle.
- The side opposite the 60° angle will be the longer leg, because 60 degrees is the mid-sized degree angle in this triangle.
- Finally , the side opposite the 90° angle will always be the largest side(Hypotenuse) because 90 degrees is the largest angle.
In 30°−60°−90° right triangle,
- the length of the hypotenuse is twice the length of the shorter leg,also
- the length of the longer leg is
times the length of the shorter leg.
Then:
the sides are in proportion i.e, 
Therefore, the ratio of the length of the longer leg to the length of its hypotenuse is: 
Answer:
We need a non-included side of one triangle
Step-by-step explanation:
By means of the AAS postulate.
The Angle-Angle-Side postulate (AAS) tells us that if two angles and a non-included side of one triangle are congruent to two angles and the corresponding non-included side of another triangle, then the two triangles are congruent.