Answer:
The NPV of the machine is closest to -$34.48
Explanation:
The net present value (NPV) of the project is the present value of the future net cash flows expected from the project less the initial cost of the project. The cash inflows from this project are the cost savings that are in a form of annuity and an amount for salvage value receivable at end of year 6. Thus, the NPV of the project is,
NPV = 4000 * [ (1 - (1+0.12)^-6) / 0.12 ] + 3000 / (1+0.12)^6 - 18000
NPV = - $34.48
Answer: c. Decline is reversible at the crisis stage, whereas it is irreversible at the dissolution stage.
Explanation: Crisis Stage; at this stage decline is still reversible if the
organisation reorganizes it ways of operations or conducting business. What they can do at this point is to carryout cutbacks and layoffs which would help reduce it's financial burden and create additional capital to run the business. At the dissolution stage nothing can be done anymore to salvage the company as it would have run into bankruptcy and would need to fold up.
The ‘SMART’ technique a tool for effective goal setting. The acronym SMART stands for Specific, Measurable, Attainable, Realistic, and Time-bound, all of which are requisites for goals. The goal “to sell a combination of six refrigerators, stoves or dishwashers to earn a bonus” is specific, measurable, attainable and realistic because Michelle has done this before. Yet the goal is not time-bound. The length of time it is required to meet is not specified in the goal.
Answer
The answer and procedures of the exercise are attached in the following archives.
Explanation
You will find the procedures, formulas or necessary explanations in the archive attached below. If you have any question ask and I will aclare your doubts kindly.
Answer:
Total slack
Explanation:
Total slack is defines as the time that tasks are delayed which will eventually affect the finishing date of a project.
Total slack can be either positive or negative. Positive slack is when delay in tasks do not affect project finish date, and negative slack are delays that affect project finish date.
Total slack is calculated as difference between smaller value of late finish and early finish.
Tom shares 4 days of his slack with the contractor.
So he has 10- 4 = 6 days slack
The total slack is 6 + 4= 10 days
In this scenario the difference between late start and early start is 9 - 5= 4 days