Answer:
The correct answer is D
lowers; probably changes, but more information is needed to determine if it increases or decreases
Explanation:
The increase in suppliers for strawberries causes the supply curve to shift to the right causing the equilibrium price to lower fro Po to P1.
The increase of price for Kiwis will move the price from Po to P1. The new price is not at equilibrium, as there has not been a shift in demand or supply as shown in the diagram.
Answer:
the average amount of money is 1,165
Explanation:
The computation of the average amount of money i.e. earned by each theater is shown below:
= Total number of tickets sold ÷ number of theaters
where,
The Total number of tickets sold is 879,575
And, the number of theaters is 755
Now place these values to the above formula
So, the average amount of money is
= $879,575 ÷ 755
= 1,165
hence, the average amount of money is 1,165
Answer: <em>Total Period Cost = $20,500</em>
Explanation:
Given :
Salary = $4000
Factory supply = $1000
Indirect labor = $6000
Direct material = $16000
Advertising expense = $2500
Office expense = $14000
Direct labor = $20000
Period costs are the costs incurring that do not tend to be a section of manufacturing process. Therefore, we compute the Period Cost using the following formula:
<em>
Period costs = Salary + Advertising expense + Office expense
</em>
<em>
= $4,000 + $2,500 + $14,000
</em>
<em>
= $20,500</em>
Answer:
B. fixed cost per unit increases
Explanation:
As we know that
If the production volume increases, the fixed cost per unit is decreases as it reflect an inverse relationship between the fixed cost per unit and the production volume
Let us take an example
Fixed cost = $20,000
Production volume = 100,000
Decrease in production volume = 80,000
So, the fixed cost per unit in the first case is
= 20,000 ÷ $100,000
= $0.2
And, the fixed cost per unit in the second case is
= 20,000 ÷ $80,000
= $0.25
Therefore, the fixed cost per unit increases
Answer: a.Working to ensure that all variances are favorable.
Explanation:
Variance Analysis is an analysis of the difference between planned and actual numbers. For example of $599 was budgeted for bills but only $500 was paid, $99 would be the Variance.
Summing Variances up gives a picture of performance for a particular period of time in relation to if one has OVER -PERFORMED or UNDER-PERFORMED
The following are steps in Effective Variance Analysis Management
1. Identifying questions and their explanations
2. Preparing standard cost performance reports
3. Taking corrective and strategic actions
4. Computing and analyzing variances.
Option A is not included therefore it is the correct option.
If you require any further clarification do react or comment.