Options:A) Present value of a single amount
B) Future value of a single amount
C) Simple interest
D) Present value of an annuity
E) Future value of an annuity
Answer:B) Future value of a single amount.
Explanation: Future value of a single amount is an accounting concept used to describe how much a single lump sum of money deposited in a bank account would have grown up to after a given period of time. Future value of a single amount can be obtained by
multiplying the principal(P)*the interest rate(I) * time(t) The interest rate is expressed as a decimal.
The FV = P(1 + rt).
Future value of a single amount is usually used in calculating the total accrued amount of fixed deposits accounts,it is a single period investment.
Answer
The answer and procedures of the exercise are attached in the following archives.
Explanation
You will find the procedures, formulas or necessary explanations in the archive attached below. If you have any question ask and I will aclare your doubts kindly.
Answer: Option A
Explanation: In simple words, ethical behavior refers to the behavior which is seen as as morally correct from the perception of the society.
In the given case, Johnson technologies is giving award to their employees based the person skill traits such as safe driving etc. Hence they are awarding their employees for traits that are considered ethical and morally correct in the eyes of law and society.
Thus, from the above we can conclude that the correct option is A.
<span>Answer;
Every time the procurement purchase or procures goods or services it is participating in the economy.
when you pay taxes to the government you are supporting the economy. Having a job to support your financial needs such as mortgages and bills will save you from going bankrupt and hurting the bank.
Explanation;
Financial decisions are important in any business, for the growth and development of the business, these includes, investments decisions, wages, purchases, loans and debtors.
These financial decisions have a direct or indirect impact on the economy; for example the purchase of goods and services impacts the economy directly, as it facilitates trade, and also the tax charged on the purchased goods and services.</span>
Answer:
Acitivy B should be crashed first by 2 days and Activity B has a crash cost per days of $25, it will be crashed for a total of $50.
Explanation:
activity A =
normal time (NT) = 5 days
Normal cost (NC) = $0
crash time (CT) = 3 days
Crash cost (CC) = $500
crash cost per day = [CC - NC]/[CT - NT] = $250/day
activity B:
normal time (NT) = 6 days
Normal cost (NC) = $0
crash time (CT) = 4 days
Crash cost (CC) = $50
crash cost per day = [CC - NC]/[CT - NT] = $25/day
activity C:
normal time (NT) = 8 days
Normal cost (NC) = $0
crash time (CT) = 3 days
Crash cost (CC) = $1000
crash cost per day = [CC - NC]/[ CT- NT] = $200/day
The activity that takes the least cost to speed up is the first one to be crashed. from the computations, activity B takes the least cost to speed up, so the project manager should crash activity B first by 2 days.
Therefore, Acitivy B should be crashed first by 2 days and Activity B has a crash cost per days of $25, it will be crashed for a total of $50.