Standard deviations of the four activities of the critical path are 1,2,4,2.
Standard deviation of this critical path = Sum of square root of variance of this corresponding critical path
Standard deviation of critical path 



Now we need to find the probability that the project will completed in 38 weeks given that its expected completion time is 40 weeks.
That is, we need to find P(X<38) :


Probability 
Thus the probability that the project will be completed in 38 weeks is 0.34.
Answer: x = 7/2
Step-by-step explanation: u juss simplify 1/2 x 7 to 7/2 so x = 7/2
Hello,
To find the Unit Price of the loaves of bread just divide the cost by the amount of loaves it costed.
5.94 / 3 = $1.98
Each loaf (Unit Price) costs $1.98!
The quadratic formula, has a part we call the "discriminant" defined by the variables that are inside the square root, and is denotated by "delta":
<span>Δ=<span>b2</span>−4ac</span>
Whenever we solve a quadratic equation that is complete and we analyze the discriminant, we can get 3 scenarios:
<span>if→Δ>0<span>=></span>∃<span>x1</span>,<span>x2</span>/a<span>x2</span>+bx+c=0</span>
This just means: "if the discriminant is greater than zero, there will exist two x-intercepts"
And for the second scenario:
<span>if→Δ=0→∃<span>xo</span>/a<span>x2</span>+bx+c=0</span>
This means: "if the discriminant is equal to zero, there will be one and only one x-intercept"
And for the last scenario:
<span>if→Δ<0→∃x∉R/a<span>x2</span>+bx+c=0</span>
This means that :"if the discriminant is less than zero, there will be no x-intercepts"
So, if we take your excercise and analyze the the discriminant:
<span>3<span>x2</span>+7x+m=y</span>
we will find the values that satisfy y=0 :
<span>3<span>x2</span>+7x+m=0</span>
And we'll analyze the discriminant:
<span>Δ=<span>72</span>−4(3)(m)</span>
And we are only interested in the values that make the discriminant equal zero:
<span><span>72</span>−4(3)(m)=0</span>
All you have to do is solve for "m".
Answer:1.3
Step-by-step explanation: