The probability that the project will be completed in 38 weeks if its expected completion time is 40 weeks
. Option (b) is correct.
Further Explanation:
The value of standard normal distribution can be obtained as follows,

Here,
is the standard normal value,
represents the mean,
represents the mean,
represents standard deviation.
Given:
The options are as follows,
(a). 
(b). 
(c). 
(d). 
Explanation:
The standard deviation can be obtained as follows,
The probability that the project will be completed in 38 weeks if its expected completion time is 40 weeks can be obtained as follows,

The probability that the project will be completed in 38 weeks if its expected completion time is 40 weeks
. Option (b) is correct.
Learn more:
- Learn more about normal distribution brainly.com/question/12698949
- Learn more about standard normal distribution brainly.com/question/13006989
- Learn more about confidence interval of mean brainly.com/question/12986589
Answer details:
Grade: College
Subject: Statistics
Chapter: Normal distribution
Keywords: four activities, critical path, 1, 2, expected completion, project, 38 weeks, 40 weeks, mean, standard normal distribution, standard deviation, test, measure, probability, low score, mean, normal distribution, percentile, percentage, proportion