Answer: Nominal
Explanation:
When the Nominal measurement scale is used, it means the data was sorted into labels or names which is why it is sometimes referred to as Named data. For instance, sorting dogs in a park into their species i.e Husky, American Bull, German Shephard etc.
There is no quantitative value and usually there is no ordering method to this measurement scale.
The professor sorted her students according to their majors which in this case acted as labels so the Professor was using the Nominal measurement scale.
Answer:
a) 2,093
b) It will reorder once there are 420 units left (demand during lead-time)
c) 34 days
Explanation:
a) economic order quantity

<u>Where:</u>
D = annual demand = 21,900
S= setup cost = ordering cost = 50
H= Holding Cost = 0.50

EOQ = 2092.844954
b) it takes four days to arrive:
if it sale 420 units per week then:
420 x 4/7 = 240 units are demand during delivery
c) order cycle:
EOQ / Annual Demand
2,093 / 21,900 = 0,09557 x 365 = 34.8333 days
It will order every 34 days (if it orders after 35 days will face shortage)
Defined the answer multiplied $80,000 by 20, once you get that answer multiply that by 0 5.25, then whatever you get is the answer. You're welcome, tea sis, shook, can't relate, be smarter
Answer:
The answer is National Labor Relations Act (Wagner Act)
Explanation:
The national labor Act of 1935 provides workers with the right to organize and join labor union. The Act also provides workers with a framework for collective bargaining. The Wagner Act prohibits the interference or coercion of workers to exercise their rights of organizing or joining labor unions alongside bargaining collectively for their working conditions or wages.
Moreover, the Act prohibits the employer from the refusal to bargain with employees' representatives.
Answer:
11400
the investment should be made because NPV is positive
Explanation:
Net present value is the present value of after-tax cash flows from an investment less the amount invested.
NPV =( Net annual cash flows x present value factor) - cost
(37300 x 5,02 ) - $175,846 = 11400