Answer: b) No
Explanation:
If you double the capacity of the bottleneck operation i.e the operation that has a limited capacity that is causing the entire project to slow down, it could work for removing the bottleneck from that particular operation. The problem however, is that this bottleneck might then be passed into another operation which will then slow down the entire process again.
Think of this this way, imagine there is constant traffic on one road with a double lane in a city and the city decides to up it to a four lane drive. The traffic subsides in that area but still continues on the road lane after the upgraded road which is a 2 lane as well.
The problem may have been fixed in one area but might just come up in another one.
Answer:
Option A
Explanation:
When you combine the costs it will be cheapest:
A - $90
B - $100
C - $110
D - $126
Hope this helps ya out fam!
Brainliest?
~theLocoCoco
Answer:
The correct option is D. integrated cost leadership/differentiation
Explanation:
Integrated cost leadership/differentiation is a business level strategy where differentiated products are offered in market at low cost.
Differentiated product signifies the unique characteristics the customer values and cost leadership signifies that the product is offered at the lower-cost, i.e., at a margin just above average costs.
It is useful in gaining wide customer base especially in a global frontier.
Answer:
The correct answer is letter "B": There is a negative correlation.
Explanation:
In the world of Finance, Correlation is a statistical measure of how two securities move in relation to each other. Correlation is represented by the correlation coefficient with ranges between (-1) and (+1). When two variables move in a similar direction, they are considered positively correlated. If the variable move in different directions they are negatively correlated.
Answer:
The answer is d
Explanation:
PV=(AP-SP) x AQ
500u=(1-x) x 10,000
500u=10,000x
x=$0.05
SP=1-0.05
=$0.95
Hope this helps! have a great day!