could you explain some more please
Answer:
d. $197,418
Explanation:
Profitability index for this project = Present value of cash inflows / Present value of cash inflows
Profitability index for this project = 2.531*$78000 / $195000
Profitability index for this project = $197,418 / $195,000
Profitability index for this project = 1.0124
So, the net present value of this project is $197,418
Answer:
The correct answer is letter "C": Exactly $396.
Explanation:
An Amortization Schedule is a table that shows the amounts of principal and interest that comprise each loan payment. Amortization schedules reveal the true cost of purchasing a home, car or requesting a student loan that is<em> paid with regular, equal installments over a period of time</em>.
Thus, <em>Roxanne should pay $396 monthly for the next 10 years</em>.
Answer:
8.27%
Explanation:
Data provided in the question:
Current price = $36.72
Annual dividend paid, D0 = $2.18
Dividend growth rate, g = 2.2% = 0.022
Now,
Cost of Equity = [ (Dividend For Next Year) ÷ Current Price ] + Growth rate
= [ ( D0 × ( 1 + g ) ) ÷ $36.72 ] + 0.022
= [ ( $2.18 × ( 1 + 0.022 ) ) ÷ $36.72 ] + 0.022
= [ 2.22796 ÷ $36.72 ] + 0.022
= 0.06067 + 0.022
= 0.08267
or
= 0.08267 × 100% = 8.267% ≈ 8.27%