Answer:
<em>6 days</em>
<em></em>
Step-by-step explanation:
Let the time taken by Carpenter working alone =
days
Then time taken by apprentice alone = Twice as that of taken by Carpenter = 2
days
Time taken working together = 2 days
Work done in one day working together = 
Work done in one day by Carpenter working alone = 
Work done in one day by apprentice working alone = 
Work done in one day by Carpenter working alone + Work done in one day by Carpenter working alone =
+
= Work done in one day working together = 

Time taken by Carpenter alone to complete the work = 3 days
Time taken by Apprentice alone to complete the work = 3
2= <em>6 days</em>
C. $360
$224x4=896 (total profit)
$896 (total) - $536 (first month profit) = $360 (second month profit)
Answer:
m∠ABE = 27°
Step-by-step explanation:
* Lets look to the figure to solve the problem
- AC is a line
- Ray BF intersects the line AC at B
- Ray BF ⊥ line AC
∴ ∠ABF and ∠CBF are right angles
∴ m∠ABF = m∠CBF = 90°
- Rays BE and BD intersect the line AC at B
∵ m∠ABE = m∠DBE ⇒ have same symbol on the figure
∴ BE is the bisector of angle ABD
∵ m∠EBF = 117°
∵ m∠EBF = m∠ABE + m∠ABF
∵ m∠ABF = 90°
∴ 117° = m∠ABE + 90°
- Subtract 90 from both sides
∴ m∠ABE = 27°
The appropriate response is the third one. A Cartesian organize framework is an arrange framework that determines each point exceptionally in a plane by a couple of numerical directions, which are the marked separations to the point from two settled opposite coordinated lines, measured in a similar unit of length. Each reference line is known as an organize pivot or only hub of the framework, and the point where they meet is its birthplace, as a rule at requested combine (0, 0).
Answer
The answer and procedures of the exercise are attached in the following archives.
Step-by-step explanation:
You will find the procedures, formulas or necessary explanations in the archive attached below. If you have any question ask and I will aclare your doubts kindly.