Answer:The product margin for product M5 is $7,385
Explanation:
To calculate the product margin for product M5,
Processing 3,870 ÷ 9,000
= 0.43 per MH
Supervising 25,000 ÷ 1,000
= $25 per batch
To calculate the overhead cost for product M5
Processing 0.43 per MH × 500
= $215
Supervising $25 per batch × 500 batches
= $12,500
Total = $12,500 + $215
= $12,715
To calculate the product margin for product M5 under activity based costing
$
Sales. 95,400
Less:
Direct materials 32,500
Direct Labour 42,800
----------------
Prime Cost. 75,300
Add: Overhead 12,715
----------------
Total Cost of production. 88,015
-----------------
Product Margin. 7,385
------------------
Answer: Both A and C
Explanation:
The Phil's filling gas station operates on a highway was solo in that area and had no other gas stations nearby.It enjoyed the profit .
Sooner a new gas station opened near Phil's gas station.The profit of the Phil's gas station started decreasing. This was because the it has to lower prices to increase its demand and as there were substitutes available in the market now, people moved to another gas stations for their need.
Both of the cases will decrease its profit.
12000*12= 14400 for a year
Answer:
The correct answer is the option C: the higher the price the higher the quantity that the sellers are willing to supply.
Explanation:
To begin with, to understand why the supply curve slopes upwards we need to understand that <u>there is a direct relationship</u> between the quantity that the suppliers are willing to sell and tha price of the product offered and therefore that when the price increases the amount that the suppliers will be willing to offer will increase due to that direct relationship and that is reason why the supply curve slopes upwards.