Answer:
3 then 1
Explanation:
Supply is said to be increased when the quantity supplied expands but the price and quantity demanded remains unchanged. As quantity supplied has increased whereas the quantity demanded is what it was before this change, there is first a surplus of bottled water in the market. This surplus will have a downward pressure on price, reducing the quantity supplied a bit and, as the law of demand suggests ,the quantity demanded will increase. Given that the demand is relatively price elastic, the change in quantity demanded will be greater than the change in price. Therefore the revenue will increase.
Answer:
The correct answer is C.
Explanation:
Giving the following information:
Total Estimated total machine-hours (MHs) 10,000
Estimated total fixed manufacturing overhead cost= $45,800
Total Estimated variable manufacturing overhead cost- per MH= $1.90 + $2.10= $4
To calculate the estimated manufacturing overhead rate we need to use the following formula:
<u>Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base</u>
<u>Estimated FIXED manufacturing overhead rate=</u> (45,800/10,000)= $4.58
Answer: $721 Unfavorable
Explanation:
The following can be deduced from the question:
Actual hours = 3690 hours
Standard hours = 3620 hours
Standard rate per hour = ($14000 + $27200) / 4000
= $41200 / 4000
= $10.30 per hour
Therefore, the overall variable overhead efficiency variance for the month is calculated as:
= (Actual Hours - Standard Hours) × Standard rate per hour
= (3690 - 3620) × $10.30
= 70 × $10.30
= $721 Unfavorable
Answer:
Explanation:
worker's production rate = 60/3 = 20units per hour
monthly capacity 160 x 20 = 3200 units.
capacity needed to produce 2000000 units
= 2000000/3200
= 625
therefore, since they already have 500 workers, they need to hire 125 more workers.
b) At the end of October they will have 2 million inventory.
c) Average inventory in each of the months has been listed in the attachment below.
Answer:
A) 100
Explanation:
total sales 3,600 units
cost per unit $200
cost of placing order $40
holding cost $20 per year
working days 360 per year
lead time 5 days
If Mark orders 200 units each time, his average inventory ?
daily sales = total sales / working days = 3,600 / 360 = 10 units per day
number of orders per year = 3,600 / 200 = 18
Mark places one order every = 360 days / 18 orders = 20 days
average inventory = (200 units / 20 days) x 10 days = 100
I assume that mark has some type of safety stock that allows him to hold enough inventory to cover for the 5 day lead time.