Answer:
Projects Y and Z
b. Projects W and Z
c. Projects W and Y
Explanation:
CAPM equation : Expected return = Risk free rate + Beta x (Expected market return - Risk free rate)
W = 4% + [0.85 x (11% - 4%)] = 9.95%
X = 4% + (0.92 x 7%) = 10.44%
Y = 4% + (1.09 x 7%) = 11.63%
Z = 4% + (1.35 x 7%) = 13.45%
Projects Y and Z have an expected return greater than 11%
b. Projects W and Z should be accepted because its expected return is higher than the IRR
c. Project W would be incorrectly rejected because the expected rate of return is less than the overall cost of capital (i.e. 9.95 is less than 11). But its expected rate of return is greater than the IRR
Y would be incorrectly accepted because its expected rate of return is greater than the overall cost of capital but its expected rate of return is less than the IRR
Answer:
C. Businesses create goods for product markets to sell.
Explanation:
Answer:
6) H0: μ≥ 7.4 versus H1: μ< 7.4
7) - 1.28
8) - 1.50
Answer:
Retiring the oldest bond
Explanation:
Firms issue bonds to raise the funds. Firm has to pay dividend on those bonds and the ability of firm to pay dividend reflect the financial position of the firm. Thus, retiring the oldest bond in exposes company to the most risk of being issued an emergency loan
Answer:
b. 10,000.
Explanation:
The number of units completed in April is given by the number of units on April 1st (3,000) added to the number of units started during April (11,000) minus the number of units still in production on April 30th (4,000):

10,000 units were completed during April.