If Ray earns $900 a week and deductions are 28% Ray's take home pay is:
$648 a week
If we assume that the deductions of 28% are taken out of the $900 weekly we will multiply 900 by 0.28 = 252. Then subtract 252 which is the deduction amount from the 900 and we end up with take home pay of $648.
Answer:
213 Unfavorable
Explanation:
Given that,
Direct labor-hours used to produce this output = 2,130
Actual variable overhead rate = $6.10 per hour
Variable overhead per hour = $6.00
The variable overhead rate variance for July:
= Direct labor-hours used to produce this output × (Actual variable overhead rate per hour - Variable overhead per hour)
= 2,130 × ($6.1 - $6)
= 213 Unfavorable
Answer:
On IRR basis projects 1, 2, 3, and 5 will be selected.
On NPV basis projects 1, 3, 5, and 6 will be selected.
Explanation:
The firm will accept or choose all the project that has a higher or equal internal rate of interest than cost of capital. However, in the given case project 4 has a lower internal rate of interest (12 percent) than the cost of capital. Thus, projects 1, 2, 3, and 5 will be chosen by the firm. While the firm has budget constraints so it will have no money for projects 4 and 6.
The firm will select all the projects with positive NPV when there is no budget constraint. But in case of budget constraint, the firm will select the project that has high NPV. Thus, Project 1, 6, 3, and 5 will be selected and there will be no money left for projects 2 and 4.
Could be a lot of things like;
Replaceable
Necessities
Long Lasting
Answer
The answer and procedures of the exercise are attached in the following archives.
Explanation
You will find the procedures, formulas or necessary explanations in the archive attached below. If you have any question ask and I will aclare your doubts kindly.