Answer:
Labor productivity is 157.083 per hours
Explanation:
Number of tires changed = 100 tire
Number of brake jobs = 6
Alignment job = 16
Number of standard crew = 6 machines
The cost of break specialist = $16 per hour
Cost to change tire = $8
Alignment costs = $14 per hour.
Given the cost of material = $2000
Overhead cost = $500
Now we have to find labor productivity hours.
Labor productivity = Output / Labor hours
Labor productivity = (100)(60) + (6)(150)+(16)(40) / (6)(8)
Labor productivity = (6000 + 900 + 640) / 48
Labor productivity = 157.083 per hours
Answer:
The correct answer is:
-$80 (d.)
Explanation:
in order to calculate this, we have to determine the total income earned from farming, and the total income that could have been earned if Ziva had done her consultancy service, and calculate the difference. This is shown as follows:
farming business
cost of seeds = $130
income from seeds = $300
Net income from farming = 300 - 130 = $170
Home-organizing service
charge per hour = $25
time spent on field that would have been used for consultancy = 10 hours
total amount that would have been earned for consultancy = 25 × 10 = $250
Difference between income earned for farming and the income that would have been earned for home-organizing serving = 170 - 250 = -$80
Note that the negative sign is there because Ziva indulged in the activity with the lesser income so she effectively made an economic loss instead of a profit (she made a negative profit).
I think the correct answer from the choices listed above is option D. <span>The rate of exchange has been fluctuating wildly this week. Rate of exchange is the one being monitored by every country every moment so it should be this the correct answer. Have a nice day.</span>
Answer:
How does Cobley connect the ideas of brands and force? ... He connects them by saying that the more weight the brand has the more effort it takes to change or move that brand.
Explanation: