Answer:
FV = 2,621,048.23
Explanation:
we will calcualte the future value of an annuity with an geometric progression:

g 0.03
r 0.092
C 5,356 ( we will save next year (52,000 x 1.03) the 10% )
n 39 (we start saving next year)

FV = 2,400,227.319
As we deposit at the first day of the year this will be an annuity-due so we will multiply by (1 +r)
FV = 2,621,048.23
Answer:
Vo = <u>C1 </u> + <u>C2 + V2</u>
1 + k (1 + K)2
Vo = <u>$129,600 </u> + <u>$129,600 + $3,200,000</u>
1 + 0.14 (1 + 0.14)2
Vo = $113,684.21 + $2,562,019.08
Vo = $2,675,703.29
The correct answer is C
Explanation:
The current value of the business equals cashflow in year 1 divided by 1 + K plus the aggregate of cashflow and sales value in year 2 divided by 1 + k raised to power 2.
Answer:
Given: Total shift time = 8 hours = 8 * 60 = 480 minutes
time required for production of one saw = 6 minutes
Demand for Bow saw = Demand for frame saw = Demand for dovetail saw = 1/2 * Demand of Tenon saw
a) Mixed model schedule:
Mixed model schedule
Product no. per batch
Bow Saw 1
Frame Saw 1
Dovetail Saw 1
Tenon Saw 2
Total 5
Therefore 2 Tenon Saw, and each bow, frame, and dovetail saws will be produced before the cycle is repeated.
b) 2 Tenon Saw, 1 bow, 1 frame, and 1 dovetail saws will be produced under production sequence for one unit production.
The length of cycle will be 5*6=30 minutes i.e. the cycle will repeat once in 30 minutes for 8 hours means totally it will repeat 16 times during one shift.
c) Number of saws Swenson produce in one shift = Number of Bow saw Swenson produce in one shift + Number of Frame saw Swenson produce in one shift + Number of Dovetail saw Swenson produce in one shift + Number of Tenon saw Swenson produce in one shift
Explanation:
Answer:
213 Unfavorable
Explanation:
Given that,
Direct labor-hours used to produce this output = 2,130
Actual variable overhead rate = $6.10 per hour
Variable overhead per hour = $6.00
The variable overhead rate variance for July:
= Direct labor-hours used to produce this output × (Actual variable overhead rate per hour - Variable overhead per hour)
= 2,130 × ($6.1 - $6)
= 213 Unfavorable
Answer:
On IRR basis projects 1, 2, 3, and 5 will be selected.
On NPV basis projects 1, 3, 5, and 6 will be selected.
Explanation:
The firm will accept or choose all the project that has a higher or equal internal rate of interest than cost of capital. However, in the given case project 4 has a lower internal rate of interest (12 percent) than the cost of capital. Thus, projects 1, 2, 3, and 5 will be chosen by the firm. While the firm has budget constraints so it will have no money for projects 4 and 6.
The firm will select all the projects with positive NPV when there is no budget constraint. But in case of budget constraint, the firm will select the project that has high NPV. Thus, Project 1, 6, 3, and 5 will be selected and there will be no money left for projects 2 and 4.