Answer:
Nami's indifferent in 3 points that lie on the different curve, the three poits
that are mentions are -
1. Point C - 5 soda and 6 pizza slices
2. Pont E - 2 soda and 11 pizza slices
3. Point F - 14 soda and 3 pizza slices.
Do check the graph,
In which x-axis is for pizza slices and Y-axis is for soda counts. The all three points are represented as E -( 2, 11), C - (5, 6), and F - ( 14, 3).
Answer:
<u>B, D</u>
Explanation:
1. Alex may be favoured in court if it was proven that Alex had signed the covenant not to compete in by force or else he would have been immediately fired from MyWaze. Then he may likely gain victory.
2. The second scenario, if Alex was involved in job at Google that wasn't going to compete with MyWaze; that is rather than going to work on creating a GPS Application for Google, Alex was hired to be a programmer for Google’s e-mail system. Since the email system does not have any competition with a GPS app he may be favoured.
There will be a total of 31,400 more rupees would 20000 euros buy at peak exchange rate than at closing point. We can buy more rupees at the peak exchange rate than at the closing point using the currency of Europe which is euro. The answer in this question is 31,400 more rupees can buy at 20000 euros.
Answer:
The Break Even Point is the Sales Value that will cover the cost of production. Meaning the Sales Value that will bring profitability to Zero
Break Even sales for Company wide = $378,000
Break Even Value for Chicago is $111,429
And Break Even Value for Minneapolis is $120,000
The Addition of both Outlets/Offices Break Even Sales is less than the Company-wide because the Offices don't share in the Common Fixed Expense as these are specific to Group reporting.
Explanation:
Answer:
Order size= $57.61 per machine hour
Explanation:
Giving the following information:
Order size:
Estimated total overhead= $581,866
Estimated total machine hours= 10,100
<u>To calculate the predetermined manufacturing overhead rate we need to use the following formula:</u>
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Order size= 581,866 / 10,100
Order size= $57.61 per machine hour