The side lengths could be 10, 24 and 26 units.
We must first find the side lengths. We use the distance formula to do this.
For RT:

For ST:

For TR:

Our side lengths, from least to greatest, are 5, 12 and 13.
To be similar but not congruent, the side lengths must have the same ratio between corresponding sides but not be the same length. 10, 24 and 26 are all 2x the original side lengths, so this works.
Answer:
25
Step-by-step explanation:
had it on khan
The given function is
f(x) = 4x - 3/2
where
f(x) = number of assignments completed
x = number of weeks required to complete the assignments
We want to find f⁻¹ (30) as an estimate of the number of weeks required to complete 30 assignments.
The procedure is as follows:
1. Set y = f(x)
y = 4x - 3/2
2. Exchange x and y
x = 4y - 3/2
3. Solve for y
4y = x + 3/2
y = (x +3/2)/4
4. Set y equal to f⁻¹ (x)
f⁻¹ (x) = (x + 3/2)/4
5. Find f⁻¹ (30)
f⁻¹ (30) = (30 + 3/2)/4 = 63/8 = 8 (approxmately)
Answer:
Pedro needs about 8 weeks to complete 30 assignments.
Answer:
a. f(n+1) = f(n) + 20
Step-by-step explanation:
The second hour, f(2) = 130 is the wage of the first hour f(1) = 110, plus 20.
_____
You have to look at the answers and understand what they mean. (This can be difficult when they are nonsense, as here.)
b — means each successive hour of pay is 110 more than the previous one. Clearly that is not the case for the sequence given
c — equates 0 to 20, total nonsense
d — equates 0 to 110, also total nonsense
Answer:
26 days
Step-by-step explanation:
If 6 days = rs. 2130
then 1 day = (2130 × 1) ÷ 6
Therefore 1 day = rs 355
For rs. 9230, the number of days he worked:
= 9230 ÷ 355
= 26 days