Answer:
The production exhibit both scope economics and scale economics. They are not mutually exclusive.
Explanation:
Looking at the scenario critically, we will clearly see the tendency of a scope economics. Scope economics basically hinges on getting a competitive advantage, essentially because of producing in large quantities and numbers. Riverside Ranger logo T-shirts exhibits this as it produce its products in large numbers, producing 1000 pieces of a particular design in 1 hour.
In same breath, we also have the scale economics exhibited by the organization. Taking a deeper look at the cost representation, we will see that the average cost tend to reduce as the production increases. Thus, an economic of scale is achieved here by leveraging on the mass and swift production style of Riverside Rangers logo T-shirts.
Answer:
$20,226
Explanation:
expected sales = 11,400 - 12,000 - 12,600
expected sales price = $7.20 - $7.50 - $7.80
expected variable cost = $3.072 - $3.20 - $3.328
total fixed costs = $31,000
if you use an excel spreadsheet you can calculate all the different possible simulations and combine all the expected sales x 3 different price levels x 3 different variable costs and 1 fixed cost. Once you get all the 27 possible solutions, you just get the average.
I attached it because there is no room here.
Answer:
The answer is: ALL THE OPTIONS ARE WRONG
Explanation:
A) In the short run, the firm will shut down if the price of its product is < $12.
B) In the long run, the firm will shut down if the price of its product is < $15.
C) The minimum value of variable cost equals the variable cost of producing 1 single unit, not the variable cost of producing 200 units.
D) If the firm's fixed costs are $500, it means that they decreased. According to the question the fixed costs were $690 (230 units x $3 per unit). So if the fixed costs decrease, then the average total cost should also decrease, not increase to $16.
Answer:
Explanation:
MPS Week 1 = 150
It takes 3 widgets for 1 WhatchaMacalit.
Widgets required Week 1 = 150 *3 = 450
Painting hours required Week 1 = 450*0.5 = 225 hours
Painting hours required Week 2 = 120*3*0.5 = 180 hours
Similarly, Week 3 = 75 hours
Week # 1 2 3
Widget paint 225 180 75